Answer / bharat raygor
shuttering area : perimeter length*height
| Is This Answer Correct ? | 1 Yes | 1 No |
to estimate shuttering form work for 1 cum of concrete 5 to 6 sqm of shuttering material required, calculate the concrete in cubic meter than multiply by 5.5 .
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / prem
work out for RCC quantity in cu.m .multipy that figure with 4 . you get shuttering quantity
| Is This Answer Correct ? | 1 Yes | 4 No |
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
1 Answers ECR, RRB, Si Precision Moulds,
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
What things you need to take care of before building a kitchen island?
what is thumb rule exactly?
what is the size of moduler bricks
what is meant by camber
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
What is specific gravity & how it is calculated
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
how much weighs a square feet of slab of 5 inches thick
during site visit if i find voilation going on,what can i do,how i act?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)