if suppose boiler has high heavy tube leakage, so in which time we feed the water in a boiler. can we stop the feed water at particular combustion temperature.
Answers were Sorted based on User's Feedback
Answer / mayur mukaty
In normal operation if boiler feed pump stop within a 1 min level goes down to become zero. For best practices when tube leakage heavily fuel feeding stop, take down the load, maintain draft , and take manually FRS system to maintain drum level as for as possible. For latest technology improvement ultra sonic senser are deployed for detection of location of tube failure.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / alok bhattacharya
When boiler is steaming, only then leak will develop because of steam pressure and faulty tube part. Now in case of heavy tube leakage, boiler must be stopped immediately and maintain drum level in order to avoid starvation and further damage of tubes. Moreover boiler need to be depressurized simultaneously.
Thanks
| Is This Answer Correct ? | 0 Yes | 0 No |
Hi,
I am assuming you want to stop the feed water to attend the tube leakage. But it is not clear what the question is about. IF the light up has been done,I do not think the flow of the water in boiler can b stopped. Secondly if light up has not been done then better to shut down the unit and properly take up tube leakage attending procedure.
| Is This Answer Correct ? | 0 Yes | 1 No |
By any way can we increase the B check hours from 300 to 500
how many safeties should be present in boiler?what are they?
4 Answers DN, Nandi, Pump Technology, Siris, Thermax,
Power plants are called CPP,IPP,LLP What is the meaning of it? And tell me some other type of powerplant names.
What are the turbine protections.
During shutdown of Steam Turbine,How do we cross the critical speed?
We know primary ,secondary air so, What is the work of Tertiary air in Thermal power plant
What is difference between Actual Drum Level and Compensated Drum Level?
Difference between islanding and house load operation.
why do we use contro fluid tank (cft)in turbo generator area(tg) in power plant?
1. what is meant by burner tilting?
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)