Answer / koshik
Brick work :-7to10 days
All concreting:-14to20days
| Is This Answer Correct ? | 11 Yes | 0 No |
Answer / dileep naik
It is depending upon weather condition.
Generally Brick & concrete work cured atleast 7days.
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / abdul aziz
Concrete 7 day 21 days depend on weather or no need curing use thermal blanket for self curing or curing compound chemicals
| Is This Answer Correct ? | 0 Yes | 0 No |
What is horizon or horizontal mining?
what will do when 7days concrete has failed and structure has constructed?
How many bricks are there in 100cft?
volume of 2 bulbs in pile of height 10' diameter 1'3''
what is the minimum and maximum thickness of plaster.?
Explain what is 1/8 on the architect ruler denotes?
What are the Noms/8hr for Concrete Work for Mason,Carpenter,Steel Fixer
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
What tor stands for in tor steel?
WHICH IS BETTER,BURNT BRICKS OR SOLID BLOCK IN CEMENT MORTAR
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)