You have casted a column above your footing, and you found out
it is off its location by 5cm. What would you Do?
Answers were Sorted based on User's Feedback
Answer / rajesh.d.v.s.p.
i don't no in site but according to my knowledge if the column is with in the core there is no problem other wise any eccentricity u have change the design considered moment with respected to axial load
that was design the column with moment+axial load
P = P+ P.e
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / prashanth
Depends upon the site condition.
Wheather it is in a basement depends.
please consult with your designer,because depends on FOS.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / suresh baria
Bring it to notice of structural engineer, Let him to give the corrective measure as he is the design auther and he is going to give the stability certificate.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / mkg
We have to go for chemical rebar of total no of steel bars at its proper location.
| Is This Answer Correct ? | 2 Yes | 3 No |
Answer / prabhakar trimukhe
because shuttring space or clear cover between bars and concrete thickness due protect the bars due to corrosion. due my experince
| Is This Answer Correct ? | 0 Yes | 2 No |
Why we take 162.2 in (d*d/162.2) to calculate weight of steel???
L/3 and l2 and 1.5l is use for reiforcement
where should the lap of a beam should be
what"s the formula to find the quantity (consumption) of cement,sand,aggregate for 1m3(1:2:4)?
11 Answers ABB, Construction, Isher, L&T, Saudi Oger, Spectra, Strati,
How to calculate quanty of steel in four leg stirrups?
mix proportion of M20 AND what are different grades below it
6 Answers B L Kashyap, L&T, Panchshil Infrastructure,
why moment is create in fixed beam. And why moment is not create in simply support beam
what is formwork in construction
What is the withdrawal force of steel nails?
Q Structural Behavior Of Statically Determinate And Indeterminate Reinforced Concrete Structure?
HOW MUCH WATER DO YOU NEED TO MIX IN TO COMPACT100M3 OF ROAD QUALITY BORROWPIT GRAVEL
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)