Answer / yogesh jadhav
as per IS 456 2000
development length formula is Ld=0.87fyd(dia)/4tbd
tbd for various concrete is M20=1.2 m25=1.4 m30=0.5 m35=1.7
m40 and above=1.9
for deform bars 60%increase the value of tbd for compression it is increse by 25%
for example m25 grade concrete and fy 415
ld=0.87*415*D/4*1.4*1.6=40.29D
for m25 and fy=500 ld=48.54D approx 50D
anchorage length=Ld+2D
straight anchorage length=SAL=AL+8D
| Is This Answer Correct ? | 79 Yes | 10 No |
Answer / sagar tiwari
lap length formula=d*50=mm
for example=12*50=600mm is the lap length of 12 mm bar
(d is the dia of bar)
| Is This Answer Correct ? | 81 Yes | 22 No |
Answer / sjtbehera
Lap length decided by devlopment length of the steel and grade of concrete. 50D generally taken as thumb rule in m20 grade. In m25 grade it is 41d.
| Is This Answer Correct ? | 27 Yes | 9 No |
Answer / bunty sharma
Developing length generally depends on the grade of concrete and grade of reinforcement.And it is decided by the given formula on the basis of IS code;456 :2000
Ld=0.87fyd/4tbd
| Is This Answer Correct ? | 19 Yes | 2 No |
Answer / harshit
IN horizontal lap is 39.5 in vertical lap is 49.5 in m25 grade
| Is This Answer Correct ? | 3 Yes | 3 No |
Permissible wastage of cement as per IS code ? In which IS code I get it?
Heat gain in buildings is best resisted by
6 Answers AIEEE, B Arch, JMC Projects, Unique Dream Builders,
How to calculate the quantity for masonry(block and plaster)?
what is mean by shear resistance in concrete?
3 Answers CCCL, Noble Consolidated Glazings, Sobha Developers,
How to calculate the sand and aggregate in concrete
what is the difference between sill beam,Tie beam and plinth beam?
what is the difference between arch dam and gravity dam. Name a gravity dam in India
6 Answers AAI Airports Authority Of India, L&T,
Pl. enlighten whether M20 grade RMC is suitable for columns & beams for 5 storied residential building
How to calculate quantity of binding wire for any kind of structures. How to calculate quantity of nails in 1 sq m shuttering.
What is the full form of APVC Pipe?
CORRECTION Kindly furnish the relation between 7 days strength & 28 days compressive strength of Cement Concrete cubes. Can you clarify whether the relation gets altered due to various WATER-CEMENT ratios and type of cements?
What is M40 _ TOR - EQ and B.F.S
0 Answers Odisha Hydro Power Corporation, Ramky, Simplex,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)