how to calculate the quantity of material in 1 cubic meter Concrete?
Answer / kashif khan
Qty of concrete= 1 cum
wet volume = 1 cum
Dry volume = 1*1.54 = 1.54
First of all we calculate the ratio of concrete e.g 1:2:4
2nd step; Sum of ratio = 1+2+4 = 7
Qty of cement = 1/7*1.54 = 0.21999 cum/0.035 = 6.2854286 bages
Qty of sand = 2/7*1.54 = 0.44 cum
Qty of crush = 4/7*1.54 = 0.88 cum
| Is This Answer Correct ? | 17 Yes | 0 No |
what is the cover used for footings, columns, beams ??? why they differ & how they arrive??
what is the yield strength of M30 grade of concrete
where does the hinged action while designing the strture
in which code refer the change of reinforcement dia defer to drawing . i.e. 12mm dai into 16mm dia.
What is IS Code ? And What is IS - 9301 ?
what is tmc ,term is used in measureing water, pls tell me 1 tmc = how many litres?
18 Answers College School Exams Tests, Irrigation, IT Consulting Services, IVRCL,
What is Purpose Difference in Stirrups For Beam & Column ?
How to find the cement, sand, Aggregate, for m20, m25 grade of concrete..?
What are the different types of civil engineering?
What is the ratio of M40 Concrete?
Previous IS steel code?Thanks.
what will be the difference in compressive test results for a 150 mm cube, a 150 mm cylinder and a 300 mm cube
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)