how to calculate the quantity of material in 1 cubic meter Concrete?
Answer / kashif khan
Qty of concrete= 1 cum
wet volume = 1 cum
Dry volume = 1*1.54 = 1.54
First of all we calculate the ratio of concrete e.g 1:2:4
2nd step; Sum of ratio = 1+2+4 = 7
Qty of cement = 1/7*1.54 = 0.21999 cum/0.035 = 6.2854286 bages
Qty of sand = 2/7*1.54 = 0.44 cum
Qty of crush = 4/7*1.54 = 0.88 cum
Is This Answer Correct ? | 17 Yes | 0 No |
what is the diffrence between grade beam and plinth beam
how to calclate the cemment for 1 cubic metre of 1:2:4 concrete
why +1 to be followed for calculating the no of bars in BBS. Please explain
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
if column length is 12'(feet) then how to take ring bar on it?
what is your role of in previous company as a construction manager
pls mail some more tecnical qustions at msaranya2610@gmail.com
Explain the various stages of the project planning process in construction?
how to calculate stirrups length for circular column
from where ican get sample papers for CET-delhi 2012
HOW MANY CEMENT BAGS ARE REQUIRED FOR 1m^2 PLASTERING AREA?
while doing floring in a room,from where one can start laying tiles.