how to calculate the quantity of material in 1 cubic meter Concrete?
Answer / kashif khan
Qty of concrete= 1 cum
wet volume = 1 cum
Dry volume = 1*1.54 = 1.54
First of all we calculate the ratio of concrete e.g 1:2:4
2nd step; Sum of ratio = 1+2+4 = 7
Qty of cement = 1/7*1.54 = 0.21999 cum/0.035 = 6.2854286 bages
Qty of sand = 2/7*1.54 = 0.44 cum
Qty of crush = 4/7*1.54 = 0.88 cum
| Is This Answer Correct ? | 17 Yes | 0 No |
If I want to lab 16 mm dia. bar with 20 mm dia bar with 40D lap length which dia.should I consider for lapping
Kindly furnish the relation between 7 days strength & 28 days compressive strength of Cement Concrete cubes. Can you clarify whether the relation gets altered due to WATER- CEMENT ratio?
What are the different approaches in designing the floors of the service reservoirs?
which is higher specific gravity or bulkdensity
Dear sir, What is the procedure for total station?How to calculate?
what is weight of asphalt concrete
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
what is the status of Brick & cube testing
From where the relationship of target strength comes in mix design(graph)
the construction of building in that primary thing is dig the soil which what depth will dig in stiff soil
What is the strength of 1:6:12 mix?
What is the absolute pressure scale?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)