Why reheater is not used after IP turbine.
Answers were Sorted based on User's Feedback
Answer / y v subba rao
The specific volume of steam coming out of ip turbine is very high. We can not accommodate re-heater in boiler which can handle such high volume steam. Design such type of boiler is very difficult and un economical. More over increase temperature of low pressure steam will not yield any additional benefit. However we have to reduce the temperature to 45 degrees before leaving to condenser. It is very difficult if we use re heater after ip turbine.
| Is This Answer Correct ? | 7 Yes | 0 No |
Answer / chinmay kumar patra(npti)
If we use re heater after IP than we can increase temperature not pressure so high enthalpy steam will not able to glide through turbine and it needs very bigger size LP turbine blades so vibration will be very high.
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / ajay ahake (npti ngpr )
Because , exhaust of IP is low pressure and high tempreture , when we reheat only tempreture increase but not pressure , that heat energy is not produce work unless it has pressure energy .... also that huge quantity steam can only use for number of LPTs .
| Is This Answer Correct ? | 0 Yes | 1 No |
if suppose boiler has high heavy tube leakage, so in which time we feed the water in a boiler. can we stop the feed water at particular combustion temperature.
Why attempration spray is used after hp heater?
5 Answers CMJ Breweries Private Ltd., Thermax,
operation
How to decide Heating surface area of boiler on their steam generating capacity?
how mony power plants in India
What is excitation current and voltage in hydro power plant ?
what are all the pre commissioning activities in WTP in power plant
why Subcritical has 60% condenser capacity
what is the real reason than natural draught cooling towers are always in hyperbolic shape
why drum level falls when one of the running coal elevations tripped?
What is the formula for find out the height of chimeny of a powerplant?
2 Answers Rosa Power Supply Company Limited, Sail,
By any way can we increase the B check hours from 300 to 500
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)