Answer / y v subba rao
The specific volume of steam coming out of ip turbine is very high. We can not accommodate re-heater in boiler which can handle such high volume steam. Design such type of boiler is very difficult and un economical. More over increase temperature of low pressure steam will not yield any additional benefit. However we have to reduce the temperature to 45 degrees before leaving to condenser. It is very difficult if we use re heater after ip turbine.
| Is This Answer Correct ? | 7 Yes | 0 No |
Answer / chinmay kumar patra(npti)
If we use re heater after IP than we can increase temperature not pressure so high enthalpy steam will not able to glide through turbine and it needs very bigger size LP turbine blades so vibration will be very high.
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / ajay ahake (npti ngpr )
Because , exhaust of IP is low pressure and high tempreture , when we reheat only tempreture increase but not pressure , that heat energy is not produce work unless it has pressure energy .... also that huge quantity steam can only use for number of LPTs .
| Is This Answer Correct ? | 0 Yes | 1 No |
what is the difference between compensated & normal drum level in boiler drum?
what is the defenation of efficiency in the high pressor boiler? what is the formila of efficiency in the high pressor boiler?
whatis means of PPA & FSA OR SFA in power plant operation
How to control cooling tower alge
1 Answers GPL, SPY Agro Industries,
why HT motor star not grounded?
Calculating Seawater consumption for SWFGD system
What are the turbine protections.
What is definition of hydrogen cell?and were are you use?
What should be the neutral and body grounding sysytem for grid (132 KV) parallel generators (440 volts)?
what's interlock relay ?
3 Answers International Mega Food Park Limited, National Power Training Institute NPTI,
why prds line tapping taken from ms line as Pri SH O/L temp & pressure is sufficient to full fill our requirement of PRDS..
what are the steps of syncronizing the generator with an infinite grid?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)