what are all the pre commissioning activities in WTP in
power plant
Answer / rajan pandey
Raw water pump should be ready by which we can take
water to creator.proper cleaning of aerator,clariflocculator
And storage tank.Dosing system like alugm Dosing,lime dosing,chlorine
dosing should be commissioned.ReadyNess of flocculator.fitting scrapper
Fitting .isolation gate operations should be cheated
| Is This Answer Correct ? | 3 Yes | 0 No |
What are the motors used in a thermal power plant? (With type and ht/lt) What voltage levels are used in a thermal power plant?
procedure of how to generate power in solar plant.
What vibration parameters are monitored in a directly coupled single cylinder turbine and generator?
whats plant?
In turbine. why they not use 320 oil?
why seal air fan is used and where it is used and where is suction taken from
What happen when the AVR of the generator fails? Will it cause power instability and total failure of the alternator?
In a thermal power plant ID Fans running with full load but boiler load is only 80 % give reason ?
9 Answers Essar, Prumatech, Tata Power,
What is difference between Actual Drum Level and Compensated Drum Level?
What is indipendant power plant
In a coal fired boiler furnace temp. is high but super heater out let temp. low what reason for this?
6 Answers ABB, Essar, Gayatri,
Difference between electrical and electronics?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)