Answer / k r kumar ranjan
Normally In Coal based thermal power plant(Either Sub or Super Critical) 60% Bypass is adopted based on condenser heat load calculation keeping 0.9 as Condenser Cleanliness Factor.
If Some designer wants to bypass 100% of generated steam, it is also possible. In fact most Nuclear Steam Turbine adopt same for same reactor shutdown process.
Increase in % capacity of bypass system increases capital cost involved in condenser cooling surface, Extraction pumps, LP Heaters, Pipe Sizing etc.
| Is This Answer Correct ? | 0 Yes | 0 No |
What is excitation current and voltage in hydro power plant ?
What vibration parameters are monitored in a directly coupled single cylinder turbine and generator?
What is difference between Actual Drum Level and Compensated Drum Level?
what are the major duties of a instrumentation engineer in a power plant.?
why oil filled transformers will be with explosion and fire often?
what is the relation between the grid voltage and generator voltage how to link up generator with grid
What will happen if the Air Preheater is placed before the Economiser?
6 Answers Bhel, KSPL, Tata Power,
.What are the equipments should run when there is a black out in power plant.
What is LB-SR.
why IBD Vent is kept at higher elevation than CBD ?
.What is drip and drain.
what are the steps of syncronizing the generator with an infinite grid?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)