what does 1 in 30 or 1 in 40 mean when constructing camber
in roads.

Answers were Sorted based on User's Feedback



what does 1 in 30 or 1 in 40 mean when constructing camber in roads. ..

Answer / saif

this is refer to slop, 1 stand for vertical & 30 or 40 stand for horizontal.

Is This Answer Correct ?    39 Yes 1 No

what does 1 in 30 or 1 in 40 mean when constructing camber in roads. ..

Answer / pankaj

1 vertical to 30 horizontal
means moving 30 units horizantaly when we moving 1 unit verticaly

Is This Answer Correct ?    20 Yes 3 No

what does 1 in 30 or 1 in 40 mean when constructing camber in roads. ..

Answer / rafiya

In book it is mentioned that 1in 30 means for 30 m wide road the crown will be 0.5 m above the edge of the road

Is This Answer Correct ?    24 Yes 9 No

what does 1 in 30 or 1 in 40 mean when constructing camber in roads. ..

Answer / n rajesh guttedat

That is slope maintain in camber construction

Is This Answer Correct ?    3 Yes 2 No

what does 1 in 30 or 1 in 40 mean when constructing camber in roads. ..

Answer / nikhil

i know that but what does the numbers signify?

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is the mixing ratio of the cement mortar for tiles fixing in floor tiles?

5 Answers   NLC, Prakash Engineers,


say you are requsituoning cement to build masonry wall made of burnt clay bricks. how many 50 kgs cement bags will you requisition for 1:5 ratio mortar joint, if they masonry wall volume is 10 m3

1 Answers  


Is Sugar a retardar or accelator or plasctizer?

5 Answers  


What is quantity of Cement and Sand required for the 1 cum brick masonry with 1:6 Ratio cement mortar.

2 Answers   RPP Infra Projects, SIL,


How many cement & sand require in 300 sq ft plaster 8mm thickness

1 Answers   Kirthi Construction,






how to calculate the chair reinforcement length in slabs, footing or anywhere??

0 Answers  


wat is meant by aerocon bricks?

6 Answers   L&T, Real Estate,


what is the service corridor?

0 Answers   NCC,


what is the permanent solution applied for restoration of leaning tower of pisa?

0 Answers  


we have a texmo make submersible water pump 5hp 10 stage what will be the total head & is it any thumb rule for calculating the head please reply urgently

3 Answers  


give me an example of a time when you had to explain some new procedures to your co-workers for quality service delivery, how did you go about it?

0 Answers  


What in your past experience or education prepares you for the position for which you are applying

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)