what does 1 in 30 or 1 in 40 mean when constructing camber
in roads.
Answers were Sorted based on User's Feedback
Answer / saif
this is refer to slop, 1 stand for vertical & 30 or 40 stand for horizontal.
| Is This Answer Correct ? | 39 Yes | 1 No |
Answer / rafiya
In book it is mentioned that 1in 30 means for 30 m wide road the crown will be 0.5 m above the edge of the road
| Is This Answer Correct ? | 26 Yes | 10 No |
Answer / n rajesh guttedat
That is slope maintain in camber construction
| Is This Answer Correct ? | 3 Yes | 2 No |
What is the formulae of percentage of steel
How may kgs. of sand make one brass ?
How much cement and sand required for 9"brick wall per square metre
0 Answers Design Space, Rugipo,
how to design and calculate materail quantity for concrete speedbreaker ?
a butt weld is specified by
How we calculate the cement for the M 15 normal concrete with aggregate size is 40 mm ?
Structural steel: For a thumb rule check in field, the allowable weight which can be hung down for 10mm dia mild steel rod, of yield value of 0, 25 KN/mm2 and applying a factor of safety 2.00, will be how many kg?
why hanger rods are used in beam
What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers
How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?
what is workability,define it?
What is the difference between 53 grade and 43 grade cement
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)