Answer / er.subramaniyan
AS Per is code welding req.20dia of steel
doing welding in three point
1.starting point
2.middle point
3.end point
welding length 5cm
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / arka
Please check IS 9417 for welding in reinforcement.
| Is This Answer Correct ? | 0 Yes | 0 No |
in which IS Code it is given. i think is 10d. full welding
form both the face of the bars.
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / thiagarajan.m
50* d. ..ie fifty times of dia of main reinforcement
| Is This Answer Correct ? | 4 Yes | 7 No |
Answer / sjtbehera
actual as per thumb rule lapping of bar is 50d required.
but it is actual depends on development length. welding is
required where 36 dia and above bar. beyond that is not
necssary.
| Is This Answer Correct ? | 0 Yes | 3 No |
WHAT IS YOUR CURRENT SALARY
crank types
do we decide reinforcement steel , based on bending moment ? give example with continous slab?
bar bending schedule?
why steel is used in rcc columns? what is its purpose?
What do you meant by gui?
rate analysis for shuttering 1:6
How and where are aqueducts built?
lap lenth
can stub column take the load as main column
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)