Mix proportion of M30 grade?????????
Answers were Sorted based on User's Feedback
Answer / abc
mix proportion of M30 -1:1:2 ,
1cum- 15.8 bags cement , mix design 11 bags /cum.
Is This Answer Correct ? | 4 Yes | 4 No |
Answer / nagul
1:1:3 is my be correct for m30 concrete but 1:1:2 for m20 concrete
Is This Answer Correct ? | 1 Yes | 5 No |
what does the track parameter mean in staad.pro?
What is grouting? Why it is done?
Is bulkage is considered in crushed sand? if yes..then what is the percentage ??
When column of building is abutting the boundary line,then suitable footing advised is
for construction of 1 cum of brickwork what is requirement of cement, sand and bricks
3 Answers Nirman Consultants, Shapoorji Pallonji Group(SPCL),
what is quick sand
In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment
how to know 28 day strength of concrete knowing 3 day or 7day strength of concrete???
100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mix of M15
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
In olden days reinforcing bars in concrete are not got rusted even till now. But recently provided steel getting rusted in concrete. what are the probable reasons?
How to Calculate in measurement RCC Colo um Spred design for Billing