M20 - 1(Cement):1(1/2)(Fine aggregate):3(Coarse aggregate)
M25 - 1(Cement):1(Fine aggregate):2 (Coarse aggregate)

Is This Answer Correct ?    78 Yes 15 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / shabarish

mM20 : 1:1.5: 3

M25 : is a design mix. & the proportion can be obtained
only on the basis of materials required & only in the lab.

Is This Answer Correct ?    51 Yes 8 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / ashish

M20 1:1.5:3
M25 1:1:2
M30 will depend upon the mix design

Is This Answer Correct ?    24 Yes 1 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / bhavna tripathi

The mix proportions for M20 & M25 both, shall be designed
by laboratory trials and designed according to BIS 10262,
383 & 456 or SP 23. The ratio 1:1.5:3 was given earlier in
IS 456 but IS 456 (2000) does not recommend volumetric
batch for even M20 and hence both should be designed as per
requirement, i.e. it depends on the type of cement,
gradation of aggregates,workability required and
importantly the water cement ratio.

Is This Answer Correct ?    24 Yes 3 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / nimmakayala

M10 manual mix, proportion is 1:3:6(C:FA:CA)
M15 manual mix, proportion is 1:2:4

> M15 are design Mix, and proportion on Weight basis (not by
volume basis) depend upon grade/type of cement, type of fine
aggregate and Coarse aggregate

However for the estimate purpose the cement can be calculated
For M15 (1:2:4)– cement is 6.37 bags/Cum
M20(1:1.5:3) Cement -8.09 bags/Cum
M25 (1:1:2)cement -12.2 bags/Cum

Is This Answer Correct ?    26 Yes 5 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / tiru

M20 1:1 1/2:3
M25 1:1:2
M30 Proportion not specified its depending upon mix design'

Is This Answer Correct ?    21 Yes 5 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / sobhanbabu

M5,M7.5,M10,M15,M20 -nominal mixes(by wt or by volume)
M25-both nominal and design mix
M30,M35,M40-design mixes(mixes designed specially in lab)

Is This Answer Correct ?    5 Yes 0 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / dasari

M20 1:1(1/2):3
M25 1:1(1/2):2
M30 1:1:2

Is This Answer Correct ?    3 Yes 3 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / aditya richie

concrete is designed by Job Mix Formulae, not just by
taking some standard values

Is This Answer Correct ?    2 Yes 5 No

What is the proportion of cement agg. and sand for M20,M25 and M30?..

Answer / muthazhagi

M 15 - 1:2:4 , M20 - 1:1.5"3 , M30 - 1:1:2

Is This Answer Correct ?    3 Yes 12 No

Post New Answer

More Civil Engineering Interview Questions

1 cum brick work CM1:6 how many bricks sand cement required brick size 8"4"3"

3 Answers  


how many spacers we need for 1 ton reinforcement? aprox.

0 Answers   ACC, J&P, LST,


i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??

0 Answers  


what is the status of Brick & cube testing

1 Answers   Ascent,


rate analysis for cement pointing 1:4 , for 100 sq m

0 Answers  






how to check aggregate quantity in stock yard

1 Answers  


which type of cement is used for RCC construction?Why?

4 Answers  


how many rods to be require in kg 10sq.m slab?

6 Answers   L&T, RRB,


how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????

0 Answers   Surya Logistics,


how much quantity of cement,sand and water required for 1 sq feet flooring work .

0 Answers   JMD Group,


What is the graphical relationship between N - Value of soil and Dia. of pile when pile length is fixed, and n - Value and length of pile when its dia. is fixed.

1 Answers  


I want to join bhel because

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)