How much overlapping required for welding the reinforcement
bars in Columns & beams
Answer Posted / sjtbehera
actual as per thumb rule lapping of bar is 50d required.
but it is actual depends on development length. welding is
required where 36 dia and above bar. beyond that is not
necssary.
| Is This Answer Correct ? | 0 Yes | 3 No |
Post New Answer View All Answers
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
RR masonry rate analysis
What is different between DI Pipe and CI pipe?
Which architectural movement is also known as jazz moderna?
how to check and keep control on the wastage of material at site
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
What you understand by richter scale?
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
1m square 20mm plastering how much of water need curing work
What is Heavy Concrete & Normal Concrete
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?