Answer / rajan
1m2 means 1m length x 1m breadth
Plastering thickness may be assumed 1.5cm.
So Qty will be .015m3.
| Is This Answer Correct ? | 3 Yes | 2 No |
Answer / vidyasagar daley
EG:If you take 12mm thickness then caclulation to be done.
for 1cum 1:3 cement mortor then
we have to consider dry density and wet density.
wet density 50% to be taken more then actual quantity so
1x1.5=1.5cum,
1.5/1+3=0.375
1CUM CEMENT WIEGHT IS1440KG/CUM,
(0.375X1440)/50KGS(one cement bag wieght)=540kgs/cum.
| Is This Answer Correct ? | 2 Yes | 2 No |
what is a louer? and for which purpose it will be used.
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
how calculate the cube strength in percentage
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
What is the zero value in quantity surveying
Thumb rules for 1.brickwork & Blockwork 2.Plastering 3.FLooring and tiles 4.Shuttering 5.Steel
Types of column foundation and how to calculate its steel quantity.
What is the diffence between prescribed mix and design mix
How to calculate plastering for elevated water storage tank
How is make concrete cube?
If a 12m main road straight is adjoined from both sides by 7.5 m road , how curves are given at corner for vehicle movement (measurement pls.)?
whate the size of bricks are avalable at site
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)