Answer / jitender kumar mishra
slab-80kg/m3 RCC
Column-160kg/m3
Beams -110 kg/m3
and 20% Encrease is account Lap, Band, weastage ect.
Is This Answer Correct ? | 6 Yes | 6 No |
Answer / hassan bin mohsin
Slab=80 to 90kg m3 for Rcc
Beam=120 to 140kg m3
Column =160 to 180 kg m3
15% increase in lapping, developing length or L brand & wastage etc
Is This Answer Correct ? | 1 Yes | 1 No |
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
What is labour rate per kg for cutting,fixing and binding of reinforcement steet..??
3 Answers GKC Projects Limited GKCPL,
how much shuttering oil required for 100 sqm shuttering?
How to fix toll charge for a particular vehicle at toll booths in a highway?
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
How to calculate canal slope curvature qty!
how much wall area covered by 1 kg of lapi(putty)
water cement ratio
Allowable wastage for ready mix concrete?
how to design a formwork for beam, how to determine the load baring capacity of the cuplock system and which is the relevant code for the same.
how to calcalate for roof beams & slab reinforcement design specified?
how to find the diameter of steel bar from steel area