PERT Chart
Answer / piyush singh
A PERT chart is a graphic representation of a project’s
schedule, showing the sequence of tasks, which tasks can be
performed simultaneously, and the critical path of tasks
that must be completed on time in order for the project to
meet its completion deadline. The chart can be constructed
with a variety of attributes, such as earliest and latest
start dates for each task, earliest and latest finish dates
for each task, and slack time between tasks. A PERT chart
can document an entire project or a key phase of a project.
The chart allows a team to avoid unrealistic timetables and
schedule expectations, to help identify and shorten tasks
that are bottlenecks, and to focus attention on most
critical tasks.
Is This Answer Correct ? | 3 Yes | 0 No |
how i can tak Quantity of mortar in block work
why we provide plastic sheet under lean concrete/pcc.?
sometimes, in a column, reinforcement is provided equally on 2 sides and sometimes on 4 sides.what will be the difference in the method of designing?
what is the cost of per cum of pile foundation?
How can I calculate the Compressive strength of cubes after 28 days of curing?Is there any formula or ration ?
What is the difference in design between Working Stress method & Limit State Method ? Briefly Explain.
Maximum foundation pressure under PRCC box is 19 T/Sqm and net safe bearing capacity is 12.65. Is it safe? pl help me
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
19 Answers DNA Infrastructure, HCC, L&T,
how to calculate quantity of concrete volume of pile with bulb
What is Current Shuttering rate (labour + materials) for Columns, Beam & Slab on Item rate basis ?
WHAT IS MIS REPORT?
Can we weld hot rolled steel ASTM A615 ?