Sr. No. Contract Code and Name Cost per Sqfoot % of total cost
A. Consultants
1 Architectural desigining 21.85173 1.2
2 Structural desigining 7.283911 0.4
3 Services 13.11104 0.7
7 Model making 1.098774 0.1
9 Plot Survey 0.137347 0.0
Total 43.83311 2.4
B. Civil Works
1 Excavation 15.96403 0.9
2 Antitermite treatment 0.106861 0.0
3 Sub structure Waterproofing, 3.965101 0.2
4 RCC works, Blockwork, Plaster, Misc civil works
966.7697 52.0
Total 986.8057 53.1
C. Finishing Works
1 FLOORING 142.01 7.6
2 Kitchen Platform with Sink 21.41376 1.2
3 Entrance lobby & signage 9.15645 0.5
4 Wood works 67.81992 3.6
5 Waterproofing 12.74205 0.7
6 Gypsum Plaster 36.52273 2.0
7 P.O.P false ceiling 6.498941 0.3
8 External Painting 20.82378 1.1
9 Internal Painting 21.26266 1.1
10 staircase painting 1.912218 0.1
11 Lift Shaft Painting 0.345885 0.0
12 Duct Painting 2.53158 0.1
13 Ceiling paint 7.623122 0.4
14 Aluminum Window 46.1979 2.5
17 M.S Railing 11.16349 0.6
18 Façade work 6.190976 0.3
Total 419.6929 22.6
D. Services
1 Plumbing& pumping 51.57279 2.8
2 CP Sanitary (Jaquar & Roca) 44.45325 2.4
3 Firefighting 23.43493 1.3
4 Electrical 76.44474 4.1
5 Lifts 82.40805 4.4
6 IBMS 16.33613 0.9
7 Solar water system 4.395096 0.2
8 DG Set 6.592644 0.4
Total 305.6376 16.4
Initial Total (A+B+C+D) 1755.969 94.4
Site eastablishment 33.01863 1.8
Electrical & water charges 1.5% 26.33954 1.4
Contingenices for temp. works 17.55969 0.9
EHS budget 8.779847 0.5
Construction Cost / Sft 1859.227 100.0
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
Can inverted beams used in pipes during construction?
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
how to calculate rate analysys of 1:6 plastering 10 sq m
Howmuch bend to be provide for 200/600 BEEM
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
How to calculate carrying capacity of the existing water supply trunkmain
Types of column foundation and how to calculate its steel quantity.
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
All aptitude question of Bechtel
Name the main components of a cad gui?
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
What are the advantages of cad software?
Why should you consider yourself fit to be hired by jindal steel.