deshuttering time for RCC for DPC over the foundation.
Answers were Sorted based on User's Feedback
Answer / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
Is This Answer Correct ? | 11 Yes | 0 No |
Answer / mani d.c.e
De shuttering Beam and Slab - 1day
Slab Bottom below 3m span-14 days
Above 3m Span 21days
Beam Bottom - below 3m span - 14dayss
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
Is This Answer Correct ? | 0 Yes | 2 No |
Ratio for 4500 psi concrete
if there is no alternative of silty sand avail near ,then how it is used in cement mortar or concreting?
Does vetrified tiles needs to be cure before fixing?
how to calculate the wind pressure
all technical question
What are the uses of alloys in daily life and how are alloys made?
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
Can we use 16mm dia bar in place of 12mm dia bar in COLUMNS? (if given dia bar is not available on site)
i want measure water capacity in 25'diameter and 7'height of water in circular storage tank in liters how?
why we use cement for concrete
i know that, the for calculating material required for concrete volume of concrete is taken 50-54 % more for wet volume. i have querry is that cement and sand volume taken more for making wet volume but in the case of aggregate why it is taken more there is no change in aggregate whether it is dry or wet.???? can you give me answer for this???
How to calculate super built up area in residential building