deshuttering time for RCC for DPC over the foundation.

Answers were Sorted based on User's Feedback



deshuttering time for RCC for DPC over the foundation...

Answer / vignesh s

For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.

Is This Answer Correct ?    11 Yes 0 No

deshuttering time for RCC for DPC over the foundation...

Answer / mani d.c.e

De shuttering Beam and Slab - 1day
Slab Bottom below 3m span-14 days
Above 3m Span 21days
Beam Bottom - below 3m span - 14dayss

Is This Answer Correct ?    8 Yes 1 No

deshuttering time for RCC for DPC over the foundation...

Answer / amit

for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.  

Is This Answer Correct ?    0 Yes 2 No

deshuttering time for RCC for DPC over the foundation...

Answer / manoj

24 HOUR

Is This Answer Correct ?    2 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

Ratio for 4500 psi concrete

0 Answers  


if there is no alternative of silty sand avail near ,then how it is used in cement mortar or concreting?

2 Answers  


Does vetrified tiles needs to be cure before fixing?

2 Answers  


how to calculate the wind pressure

1 Answers  


all technical question

0 Answers   L&T,






What are the uses of alloys in daily life and how are alloys made?

0 Answers  


What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?

0 Answers   L&T,


Can we use 16mm dia bar in place of 12mm dia bar in COLUMNS? (if given dia bar is not available on site)

5 Answers   Clover, Rites,


i want measure water capacity in 25'diameter and 7'height of water in circular storage tank in liters how?

7 Answers  


why we use cement for concrete

7 Answers  


i know that, the for calculating material required for concrete volume of concrete is taken 50-54 % more for wet volume. i have querry is that cement and sand volume taken more for making wet volume but in the case of aggregate why it is taken more there is no change in aggregate whether it is dry or wet.???? can you give me answer for this???

0 Answers   QRI,


How to calculate super built up area in residential building

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)