Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

deshuttering time for RCC for DPC over the foundation.

Answer Posted / vignesh s

For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.

Is This Answer Correct ?    11 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?

2087


PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.

2584


how i convert mm into standard wire guage (SWG)no.

3079


Define relative co-ordinates?

1147


Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.

2867


what are the types of dimensioning?

2306


What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?

2604


we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?

2365


How does siphoning work?

1428


Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?

1884


can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?

2580


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

2031


What is the diff b/w ROAD TUNNEL & RAILWAY TUNNEL ??

2371


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2104


Calculation of Pier Cap with tapper area?

6350