deshuttering time for RCC for DPC over the foundation.
Answer Posted / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
What is the force exerted by the tacoma narrows bridge?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
How and where are aqueducts built?
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
What is geopolymer based concrete?
how to take concrete quantity for precast segment for viaduct project?
What things architect have to take care of before starting any project?
What in your past experience or education prepares you for the position for which you are applying
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
how to calculate load bearing column
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar