deshuttering time for RCC for DPC over the foundation.
Answer Posted / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
Explain the Strength of brick?
what energized you to complete your course?
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
residential projects,structural.
what is called the inverd level of mabhole chamber?
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
What is the difference between shear and tensile strength?
What is soil enforcement?
How to find the cuplock pipe qty in staging for Minor bridge?
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
what is your role of in previous company as a construction manager
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
What is construction mitigation management?
How to calculate carrying capacity of the existing water supply trunkmain
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?