deshuttering time for RCC for DPC over the foundation.
Answer Posted / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
Volume of 25kg putty bag & 40 kg putty bag volume??
How do you change a dimension value in solidsworks?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
how to clculate the %of concrete strenght achive after curing?load
strength vs shape factor
how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.
How to make a c++ program that converts any base to base 10?
what are the types of design? which type of method is used at what type of design & why?
difference between trapezoidal and pedestal footing and how the load acts on that
What is an ortho mode?
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
what are the changes in concrete pour height as per IS 456, 2009?