Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is meant by hidden beam & purpose of hidden beam

Answers were Sorted based on User's Feedback



what is meant by hidden beam & purpose of hidden beam..

Answer / imran k tamboli

Hidden Beam is a structural member in RCC framed structure same as of normal beam, but it is provided in slab thickness only and not lumped beyound slab depth, the main reason is for this beam is to hide unnessery downward lump of beam in below floor, and we can construct brick work over it.

Is This Answer Correct ?    20 Yes 0 No

what is meant by hidden beam & purpose of hidden beam..

Answer / civil engineer

concield beam.

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is education Cess.

0 Answers  


List out the densities of different construction materials such as brick, steel, sand, aggregate etc...

19 Answers   Happy Homes, Sand,


How many steel is require in one sqft area?

17 Answers   L&T, XYZ,


what is the meaning of sleeves in reinforced concrete????. where its coming???.

1 Answers  


convert 1 guntha = how many wars or 1 war = how many gunthas

5 Answers   Shaw,


The corrosion resistance of a material is.

4 Answers  


What is thumb rule for deep trench excavation

0 Answers  


Why we add salt in silt content test of sand? Full reason ?

1 Answers   CCCL, JSW,


How to Calculate no.of bricks in 1sq.mtr

3 Answers   SADC,


how much aggregate need for 1:4:8 p.c.c in 1sqm area?

5 Answers  


What is the curing period for Epoxy grouts

1 Answers  


while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.

0 Answers   XYZ,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)