what will do when 7days concrete has failed and structure has
constructed?
Answers were Sorted based on User's Feedback
Answer / modipraveen
Hi,
Generally we will wait for 28th day test, If structure is
failure, then will intimate to Structural Consultant to
strengthen the structure.
| Is This Answer Correct ? | 19 Yes | 1 No |
If 7 days result not getting,wait for 28 days.if 28 days
result not achived that perticular Quantity part breakdawn.
in any doubt with cube testing result we can also doing
core cutter test or rebound hammer test for at the 07 days
& 28 days sharp time period
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / suresh bariya
Generally we will wait for 28th day test,if 28 days test
result get failed then immidiate inform your structural
consultant,consultant will suggest the rebound hammer test
which is not a perfect solution, then do the core cutting
test it will give you the actual result of that strucutural
concrete, from this result you will know the actual
strength ,it will decide the jacketing will serve the
purpose or brecking is the final solution.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / amilineni s babu
we have to wait for 28 days strength if it is also less we
have to go for core cutting or rebound hammer tests for that
particular structure part.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / karnam seenu
,When a cube test conducted for a structural member fails, it is advisable to go immediately for a core cutting test and send the sample slab core to test the compressive strength. You need not wait for 14 days or 28 days.
| Is This Answer Correct ? | 0 Yes | 0 No |
how to find ssm in foundation?
wat happens to the foundation when only live & dead loads are considered( wind load is excluded) during the design of tall structures. options are: a)only settlement in the internal structure and not external structure b)only settlement in the external structure and not internal structure c)no differential settlement d)none of the above
4 Answers BBJ Construction, IOCL,
Explain what are the phases inspections are done by local authority while construction?
how many bags of cement are needed to make a cement mortar of 1:3
5 Answers ABC, DBL, DHFL Dewan Housing Finance Corporation, VV, WADAN,
How many types bend used in civil reinforcing
what is the strength [final]of grade m 15 to m 45
difference between specification and method of statement
what discoveries did you have in relation to your course?
Which are the top apps for you civil engineering?
What is limit state method and working stress method and ultimate method
What is the difference between routing maintenance and major maintenance in school facilities?
where we use one way slab and two way slab?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)