Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what will do when 7days concrete has failed and structure has
constructed?

Answers were Sorted based on User's Feedback



what will do when 7days concrete has failed and structure has constructed?..

Answer / modipraveen

Hi,
Generally we will wait for 28th day test, If structure is
failure, then will intimate to Structural Consultant to
strengthen the structure.

Is This Answer Correct ?    19 Yes 1 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / vimal prajapati

If 7 days result not getting,wait for 28 days.if 28 days
result not achived that perticular Quantity part breakdawn.

in any doubt with cube testing result we can also doing
core cutter test or rebound hammer test for at the 07 days
& 28 days sharp time period

Is This Answer Correct ?    4 Yes 1 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / suresh bariya

Generally we will wait for 28th day test,if 28 days test
result get failed then immidiate inform your structural
consultant,consultant will suggest the rebound hammer test
which is not a perfect solution, then do the core cutting
test it will give you the actual result of that strucutural
concrete, from this result you will know the actual
strength ,it will decide the jacketing will serve the
purpose or brecking is the final solution.

Is This Answer Correct ?    2 Yes 0 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / amilineni s babu

we have to wait for 28 days strength if it is also less we
have to go for core cutting or rebound hammer tests for that
particular structure part.

Is This Answer Correct ?    1 Yes 0 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / karnam seenu

,When a cube test conducted for a structural member fails, it is advisable to go immediately for a core cutting test and send the sample slab core to test the compressive strength. You need not wait for 14 days or 28 days.

Is This Answer Correct ?    0 Yes 0 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / suhana soni

i want to know.

Is This Answer Correct ?    0 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

how to find ssm in foundation?

0 Answers  


wat happens to the foundation when only live & dead loads are considered( wind load is excluded) during the design of tall structures. options are: a)only settlement in the internal structure and not external structure b)only settlement in the external structure and not internal structure c)no differential settlement d)none of the above

4 Answers   BBJ Construction, IOCL,


Explain what are the phases inspections are done by local authority while construction?

0 Answers  


how many bags of cement are needed to make a cement mortar of 1:3

5 Answers   ABC, DBL, DHFL Dewan Housing Finance Corporation, VV, WADAN,


How many types bend used in civil reinforcing

1 Answers   HARIOM TMT,


what is the strength [final]of grade m 15 to m 45

2 Answers  


difference between specification and method of statement

3 Answers   L&T,


what discoveries did you have in relation to your course?

0 Answers  


Which are the top apps for you civil engineering?

0 Answers  


What is limit state method and working stress method and ultimate method

0 Answers  


What is the difference between routing maintenance and major maintenance in school facilities?

0 Answers  


where we use one way slab and two way slab?

7 Answers   SRM,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)