Answer / er. shivam dixit

construction joints are provide at the end of days work by
means when days work is end then the joints are provided for
next day work is known as construction joints.

contraction joints are those joints which are provided for
shrinking action of concrete.

Expansion joints are provided for thermal expansion

Is This Answer Correct ?    21 Yes 1 No

Tell me about Construction, Contraction and Expansion joints.....

Answer / souvik sadhukhan

construction joints are the joint provided to joint the next portion of the portion of the wall , slab or column etc.
expand joint are provided for tharmal expantion.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.

0 Answers  


Quality control

1 Answers   NCCL,


is their any instrument which can detect steel after casting of slab,etc. for verification of steel in slab,etc.

1 Answers  


How to check percentage of bulkage of sand in RCC?

4 Answers  


significance of specific surface area of particles?

0 Answers   Gammon,






why bent up bars in slab provided in alternate manner and not continuos ?

2 Answers  


93 sqmtrs area how many sand and how many cement is requir in 1;5 ratio

1 Answers   Godrej,


How to calculate numbers of carpenter, fitter, mason, unskilled worker on the basis of built up area or floor plat area of building?

2 Answers   L&T,


Explain what is the difference between built area and super built up area?

0 Answers  


why cylinder for split tensile strength test ?

1 Answers   HCC,


Whr should a joint be located in a beam if the provision of a joint is unavoidable??

2 Answers   BMTC,


how many no of cement bags required for 1:4 plastering for 100 sqft? how many no of cement bags required for 1:3 plastering for ceiling for 100 sqft?

6 Answers   Sobha Developers,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)