How much binding wire required in 1 MT Reinforcement?
How much Nails Required in 1 Sqmtr Area work progressed
Answer / sohan jaswal
For 1mt of steel, 8 to 10kg of binding wire is required.
Fir 1sqm of shuttering- 100 to 150 gm of nails are used.
| Is This Answer Correct ? | 16 Yes | 0 No |
what is relation between SPT N value and driving piles after conducting a soil test?
In the roof of a pumping station explain briefly the components of a waterproofing system?
what is the diffrence between Specific gravity & Density??
What is the percentage of steel in 1cu.m. RCC?
what is the IS code no. for concrete wastage?
What is the allowable silt content for concrete works?
What are the structural steel & where they are used
How gate result to cube for 7 day? Formula for the cube testing?
1 Answers Ambuja, Indiabulls, Legacy,
can u use instead of water milk for concreting
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
why cracks develop at the upper corners of doors openings
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)