How much binding wire required in 1 MT Reinforcement?
How much Nails Required in 1 Sqmtr Area work progressed
Answer / sohan jaswal
For 1mt of steel, 8 to 10kg of binding wire is required.
Fir 1sqm of shuttering- 100 to 150 gm of nails are used.
Is This Answer Correct ? | 16 Yes | 0 No |
what is the advantage of electronic theodolite over transit theodolite?
how to reduce heat of hydration in concrete?
An invisible line should intersect a visible line with
1 Answers PSC, PSCI, SPC Systems,
What is the strength of cement?
How to calculate the sand and aggregate in concrete
why we are doing post tensioning in beams and slabs. it is economical compare to rcc? how?
what is the difference between onw way slab & two way slab?
what is the problem not getting 7 days slab cycle in Mivan formwork? what is the output of mivan carpenter per day?
What is bylayer?
HOW CAN I CALCULATE BENTUP BAR'S INCLIND DISTANCE ?
How to do base isolation using ETABS software?
How much steel required in 1 square feet slab?