what will do when 7days concrete has failed and structure has
constructed?
Answer Posted / suresh bariya
Generally we will wait for 28th day test,if 28 days test
result get failed then immidiate inform your structural
consultant,consultant will suggest the rebound hammer test
which is not a perfect solution, then do the core cutting
test it will give you the actual result of that strucutural
concrete, from this result you will know the actual
strength ,it will decide the jacketing will serve the
purpose or brecking is the final solution.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
Consumption of Binding wire for fixing of cover block in vertical surface
Define the various stages of the project planning process in construction.
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
What is meant by a context menu in a cad software?
how much shouid be the rate for ready mix concrete per cubic meter
why & what is perchatage we are using fly ash in concrete?
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
what are the types of design? which type of method is used at what type of design & why?
How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
What is bmc stands for in bmc software?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils