Answer / santosh singh
about 9 to 13 kg of binding wire is required per ton of
steel
| Is This Answer Correct ? | 10 Yes | 6 No |
Answer / saalim
1 to 1.5 kg per quintal
ie 10 to 15 kgs per tonne depending upon dia of steel.
| Is This Answer Correct ? | 6 Yes | 2 No |
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
how many bricks required for below volume 1. depth filling 0.00 Qty 1.61 & Unit Cu.M 2. D-Filling 300 Qty 2.0 & Unit Cu.M 3. D.Filling 450 Qty 2.24 & Unit CU.M 4. D-Filling 600 Qty 2.44 & Unit Cu.M
what is a civil enggineer ?
How many different between estimated quantity and practical work at site.
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
Why camber is provided?
2 Answers G R InfraProjects, Tata Steel Limited,
What Is the meaning of M15 and M20
How much lap length provided in compression and tension in bridges?
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
What is the thumb rule for calculating the number of chairs in slab?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)