binding wire requirement in rcc structures
Answers were Sorted based on User's Feedback
Answer / santosh singh
about 9 to 13 kg of binding wire is required per ton of
steel
| Is This Answer Correct ? | 10 Yes | 6 No |
Answer / saalim
1 to 1.5 kg per quintal
ie 10 to 15 kgs per tonne depending upon dia of steel.
| Is This Answer Correct ? | 6 Yes | 2 No |
why cracks develop at the upper corners of doors openings
what is slope provided to lying the sewerage pipe of different dia ?
1. why we use inverted beam ? 2.why we use extra bar in beam ? 3.dimension in L-bar in column ,footing and beam
in moon night and stars r shining with moon n u stand n lloking towards sky if u have no copass, and no any other civil lab equipment, then how u point out the North direction for serveying??
sir, please send me the web address of chennai railway to know the online examresults of junior engineer[civil].
difference between high rise & multistoried building?
how to calculate cost for MS plate shuttering (show calculation/assumptions)
Explain what is Critical Path Method (C.P.M)?
extra how much quantity need to fill the actual excavated quantity.
Where can I get a Text Book on Design of Blast Resistant Buildings in PDF form.
what is 3.14 indicates for cutting length of stirrups
What is the minimum depth of a slab?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)