A bill was raised by contractor which read as follows
1.) Excavation in normal soil upto 1.5m - 250 cum
2.) Excavation in normal soil 1.5m to 3m - 240 cum
3.) Excavation in soft rock - 350 cum
4.) Excavation in hard rock - 250 cum
5.) Filling with available soil - 825 cum
6.) Filling with bought out soil - 1100 cum

How can I verify the above quantities, especially for item
no. 5 & 6?
What checks are necessary before releasing the bill ?

Answers were Sorted based on User's Feedback



A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 25..

Answer / murali vasudevan

In the extant case the total excavation is
250+240+350+250=1090 CuM. Quantity of filling = 1090 -
(Minus) Quantity of Concrete or other materials that have
gone in to the foundation below Ground Level. (For Eg Take
this as 200 Cum. Then filling required = 1090 - 200 = 890
CuM. But the actual qty of soil required will be less than
890 when we consider the bulking of excavated
sand/materials. So in practise the Qty of soil required for
re-filling the excavated portion = 890-5% of 890 = 845.5
CuM.

Another elaboration is as follows :-

Total Excavation = A
Total materials used for foundation
(Concrete+Rubble+Brick etc) = B
Material required for refilling = C = (A-B)- (A-B)*5/100


Hope this solves your problem..

Is This Answer Correct ?    12 Yes 1 No

A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 25..

Answer / gkreddy

contractor should be ansure there must
and should maitain JMR( Joint
Measurement Record) for produce the bill
otherwise bill should be rejected.claint
also insist the contractor to maitain JMR.

Is This Answer Correct ?    2 Yes 0 No

A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 25..

Answer / kirshnamurthy

both answers are coreect

Is This Answer Correct ?    1 Yes 0 No

A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 25..

Answer / u.arunkarthick

here the total excavation qty is 1090 m3, then minus the qty
of concrete used for footing and add consolidation of soil
as 2 to 3%, example if we excavate 1m*1m*1m = 1m3 of
excavated earth is there, then refill that area needs 1.2m3
because of soil consolidation.

Is This Answer Correct ?    1 Yes 0 No

A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 25..

Answer / rao

The total qty of filling should always be less than or
equal to the total qty of excavation of all types of soils.

Here in this case, the total qty of filling exceeds the
total qty of excavation, Hence the contractor has raised a
incorrect bill.

Before releasing the bill, the quantities are to be cross
checked with drawings and also practically on site visit.

Is This Answer Correct ?    3 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

What is the capacity of Maharashtra in power generation by winds?

5 Answers   MPSC, State Bank Of India SBI,


HOW TO PARKING SPACE HS CALCULATED IN MULTISTORY BUILDING?

1 Answers  


WHAT IS THE DIFFERENCE BETWEEN FACTOR OF SAFETY AND PARTIAL SAFETY FACTOR?

1 Answers  


How to calculate water cement ratio in mix desion

2 Answers   Delta,


How to find beam R/F cutting length

0 Answers  






Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire

0 Answers   BPSL,


whaat is blister in box girder bridge and what is its function..

0 Answers  


WHAT IS MEANT BY ZERO VALUE IN QUANTITY SURVEYING

1 Answers  


How much shuttering oil required for per m2 shuttering by 12mm ply

3 Answers  


An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.

0 Answers  


what is difference between 33, 43 and 53 grade cement..? which is more suitable for construction and why,..??

3 Answers  


why we use minimum cement as given in IS mix design code

5 Answers   BARC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)