Providing cement based water proofing treatment to terrace
(Indian water proofing) with brick bats with cement morter
(1:5) and (1:3).
what are rate in cum or sqm.




Answers were Sorted based on User's Feedback



Providing cement based water proofing treatment to terrace (Indian water proofing) with brick bats..

Answer / vikas kumar chauhan

Rate will be in Sqm.
This type of water proofing is called Brick Bat Coba in
which thickness of Brick Bat & Cement mortar layers also
pre-defined.

Is This Answer Correct ?    1 Yes 0 No

Providing cement based water proofing treatment to terrace (Indian water proofing) with brick bats..

Answer / ashish deshpande

depending upon locations and prise of materials and labour

Is This Answer Correct ?    0 Yes 0 No

Providing cement based water proofing treatment to terrace (Indian water proofing) with brick bats..

Answer / rustam jamal

Rate in Sq.M = Rs. 950/-
In Cum = Rs. 8482/- Per Cum

Is This Answer Correct ?    0 Yes 0 No



Post New Answer



More Civil Engineering Interview Questions

Let suppose A building wall is 12 ft high and 30 ft long and labour cost is 100 rupee per feet so calculate the total cost of labour and also explain in detail...plz ans me immadiately i am hurry Thanx

1 Answers  


What is a MIS report?

1 Answers   NCC,


The relation between cube strength & cylinder strength because––

2 Answers  


Ultimate strength to cement is provided by which chemical?

1 Answers  


please help me to find a mix design ratio for M40....

2 Answers  






mix design concrete m30 for elevated water tank

2 Answers   SITM,


how to conversation of all construction material in to brass

1 Answers   Lafarge, L&T,


methode of psc girder stressing

2 Answers   Bechtel, Simplex,


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

0 Answers  


why we do multiply 1.54 for dry volume of concrete?

10 Answers   ACC,


Water absorption for stone and first class stone bricks?

2 Answers  


Mix proportions of m30,m35,m40

2 Answers   L&T,






Categories
  • Civil Engineering Interview Questions Civil Engineering (4646)
  • Mechanical Engineering Interview Questions Mechanical Engineering (3704)
  • Electrical Engineering Interview Questions Electrical Engineering (15794)
  • Electronics Communications Interview Questions Electronics Communications (2638)
  • Chemical Engineering Interview Questions Chemical Engineering (763)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (79)
  • Bio Engineering Interview Questions Bio Engineering (30)
  • Metallurgy Interview Questions Metallurgy (95)
  • Industrial Engineering Interview Questions Industrial Engineering (199)
  • Instrumentation Interview Questions Instrumentation (2884)
  • Automobile Engineering Interview Questions Automobile Engineering (171)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (41)
  • Marine Engineering Interview Questions Marine Engineering (62)
  • Power Plant Engineering Interview Questions Power Plant Engineering (170)
  • Engineering AllOther Interview Questions Engineering AllOther (1336)