what is procedure to find the volume of material in M20
concrete?
Answer Posted / i.rajamohamed. p.s.y.e.college
M20 ratio is 1:1.5:3( TAKE 20mm aggregate)
(i)add ratio= 1+1.5+3= 5.5
(a) volume of aggregate = 1\7*1.57 = 0.22m3
(b) volume of sand =1.5/7*1.57= 0.33m3
(c) volume of cement =3/7*1.57 = 0.67m3*1440=964 kg.
(note: 1.57 for 1m3 box)
Is This Answer Correct ? | 5 Yes | 16 No |
Post New Answer View All Answers
how much cement and sand required for 1cum rr masonry
why development length = 50D . why not 100D
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
What is the difference between undo & redo?
Technical Question of Civil Engineering
rate analysis for cement pointing 1:4 , for 100 sq m
how many shuttering material required for 1000 sq.m built up area.
For what building Built-on balconies are preferable? What are the advantages?
how to caluclate sienerge qty in construction in ap
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
why we use aggregate,sand with cement in concrete?
can you give me the details of rate analysis of steel and concrete?
how to do cementicious paint for rcc walls of cw pump house
What is c.g.i sheet which used for roof??