Answer / selvaraj
I can find this qty by two methods volume basis and weight basis.
Volume basis-ex m15 is 1:2:4 .sum all and kept on detominator and the what mat will be req us ,put on value top.for cement (1/7)x1440.its give kg/m3.
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / ravi pratap singh tomar
Concrete Mix Design is the name of procedure...it can be performed by BIS or ASTM standerds.
things to be known/assumed:-
1.compressive strength of 28days
2.maximum size and type of aggegate
3.degree of qulity of controll,workability and
4. type of exposure/type of cement etc
procedure:-
1. find target mean strength-by Ft=Fck+1.65*s(s-std deviation ,varries w.r.t grade of conc.)
2. water cement ratio- this find with the help of a graph W/C ratio Vs Fck.approximate air contant s found by another table wrt aggre gates s max size.(genrally-0.6to .35)
3.find workabiliti den multiply by 0.8follow a table to find zone nd % of sand .
4.now cement ,voids sand water are known along with total aggregate then finally using a specific formula given in BIS course and fine aggregates r also estimated.
| Is This Answer Correct ? | 1 Yes | 10 No |
what is meant by belt in house construction?
Discuss some applications of modular elasticity?
what is plum & mass concrete?
which has high compressive strength between hollow block and brick masonry?
Significance/Uses/effect of Rolling Margin ?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
Soil is clay
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
0 Answers AIZAZ General Contracting General Maintenance, GK Realtors,
Unit weight of brick? Sand? Aggregate? Steel? Cement? Water?
28 Answers Aliens Group, Cemplex, DLF, L&T, LBC, Power Trade Engineering, Vishnu, VKM,
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
what could be the production cost of 1 cum of concrete by CP30 plant
What is Architect-Prepared Contract?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)