how much cement,sand,aggregate will use for 1 cum in ratio of
1:2:4.
Answers were Sorted based on User's Feedback
Answer / karim
Quantity: 1cum
Proportion: 1:2:4[M15]
Add 54% extra
[54/100×1]+1=1.54cum
Cement required =1.54/7=0.22cum
We know: 1bag cement=0.0347cum
So, No of bags of cement =0.22/0.0347=6.34bags
Sand required: [1.54/7]×2=0.44cum
1cum=35.347cft
So 0.44cum=15.55cft
Aggregate required =[1.54/7]×4=0.88cum
So,0.88cum=31.18cft
Finally,
[Cement required =6.34bags
Sand=15.55cft
Aggregate =31.18cft]
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / seduraman
m15 1:2:4 (7 parts)
cement 1/7 x 1.57 = 0.225
Sand 2/7 x 1.57 = 0.45
Jelly 4/7 x 1.57 = 0.90
Cement : 0.225 x1440 = 324kg
Total nos of bag of cement : 324/50 = 6.48 Bags of cement
| Is This Answer Correct ? | 4 Yes | 5 No |
Answer / huner
v=1c*2s*4G (1+2+4)=7
so for 1 cu m3 1/7= 0.15
the unit weigh of cement =1400 kg/m3
hence for
cement 0.15*1400 =210 kg
sand 2*0.15=0.3 m3
Gravel 4*.15 =0.16 m3
| Is This Answer Correct ? | 16 Yes | 18 No |
Cement - 6.38,Sand -2.12cft,Aggregate - 4.59cft
| Is This Answer Correct ? | 6 Yes | 8 No |
Answer / er. nirakar behera
Ratio of concrete mix is 1:2:4
we have to calaculate only about the dry volume.
dry density of concrete =14.2qntl/cum
volume of concrete =
1.54/(1+2+4)=0.22cum
Hence for weight of mix ingredients=(14.2qntl/cum*0.22cum)
i.e=3.124qntl
required weight of cement=1*3.124qntl=3.124qntl or say
6.2 bags
for sand =2*6.2cft=12.4 cft
for aggregate=4*6.2cft=24.8cft
| Is This Answer Correct ? | 3 Yes | 6 No |
Answer / a.mohammed yahya
For all Common Grade of Concrete Quantity 1Cum fill the
1.57Cum(for 20mm size Jally)
So For the Ratio = 1: 2: 4 (Total = 1+2+4=8)
( there for 1 - Cement,2- sand,3- 20mm Size Jelly)
Calculate for Cement = 1/8 = 0.125
= 0.125 x 1.57
= 0.196
For Common 1Cum Cement Quantity = 1440kg
there for = 1440 x 0.196
Required Cement = 282kg
Calculate for Sand = 2/8 = 0.25
= 0.25x 1.57=0.393Cum
= 0.393 x 35.32
Required Sand =14 Cft
Calculate For Jelly = 4/8 = 0.5
= 0.5 x 1.57
= 0.79Cum
Required Jally = 0.79 x 35.32 = 28 cft
| Is This Answer Correct ? | 24 Yes | 33 No |
CM 1:4 !:5..what CM stands for?? and what is standard ratio used for external plaster??
mix design procedure for 1:6 cement mortar
What are the various load combination in Limit state method?
2 Answers Developer Building Contracting, DMRC, Engineers India Limited,
What is reinforced brick masonary and its advantages and applications, arrangement of steel
If i buy some material and the seller asks me my TIN number what does that mean?? Is it my Taxpayers Identification number or it is my Tax invoice number? What does both of these stands for???
what is meant by concrete joints?
which type of foundation are most prefarable in blockcotton soils
What Should be the CBR Value for Transported (Selected) Soil.whether it can be 5% or not ?
Explain soil analysis?
What are the causes of failure of foundations and remedial measures?
I want to construct 1850 square ft of rcc apartment , with stilth parking , the site requires 18 ft of pile foundation , the apartment will be above ground parking , can some one guide me about the cost of construction of such structure in Pune ?
explain the difference between short column and long column
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)