how much cement,sand,aggregate will use for 1 cum in ratio of
1:2:4.
Answer Posted / seduraman
m15 1:2:4 (7 parts)
cement 1/7 x 1.57 = 0.225
Sand 2/7 x 1.57 = 0.45
Jelly 4/7 x 1.57 = 0.90
Cement : 0.225 x1440 = 324kg
Total nos of bag of cement : 324/50 = 6.48 Bags of cement
| Is This Answer Correct ? | 4 Yes | 5 No |
Post New Answer View All Answers
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
Which prize is the alternative to the NOVEL Prize?
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
Technical Question of Civil Engineering
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
i need gate exam civil engineering question papers with answers
What is the diff between cad & cadd?
explain what do you mean by the property development.
What is the development length given in pile?
What is factor not to be taken in consideration in mix design?
what is polity
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
How you can use different dimension tools in cad? What are the different dimensions available?