how much cement,sand,aggregate will use for 1 cum in ratio of
1:2:4.
Answers were Sorted based on User's Feedback
Answer / lakshmanarajan
The Ratio is 1:2:4 Total = 7
Ingredients of this Mixture is = 1.57
So the qty of Cement is = (1/7) x 1.57 = 0.224 cum
Volume of cement in i cum = 1440kg
therefore required cement = 1440 x 0.224 = 322.56kg
Weight of 1 cement bag is = 50 kg
so 322.56/50 = 6.45Bag
Add 5% for wastage = 6.45 x (5/100) = 6.77 bag required
Qty of Sand = (2/7) x 1.57 = 0.448 cum (1cum = 35.31 cuft)
convert cum to cuft = 0.448*35.31 = 15.18 cuft
Sand is available in unit,so 1 unit = 100 cuft
So required qty of sand is = 15.18/100 = 0.151 unit require
Qty of Aggregate = (4/7) x 1.57 = 0.89cum
Convert cum to cuft = 0.89 * 35.31 = 31.42cuft
sand & Aggregate also available in unit
so above the same as aggregate = 31.42/100 = 0.314 unit require
| Is This Answer Correct ? | 85 Yes | 12 No |
Answer / roys
Ratio of concrete mix =1:2:4 (Calculation for 1cum)
Cement:-
1/7*1.54=.22 cum [1.54for dry volume]
=.22/0.0345
=6.38bags
Sand:-
2/7*.22=0.06cum
=0.06*35.32
=2.12cft
Aggregate:-
4/7*.22=0.13cum
=0.13*35.32
=4.59cft
| Is This Answer Correct ? | 61 Yes | 24 No |
Answer / mr. b.nagaraj
as per is 6.4 bags of cement & 0.86m3 / 30.31cft of 20mm
aggregate & 0.46m3 / 16.25cft of sand requires for 1m3 of
m15 concrete or 1:2:4
| Is This Answer Correct ? | 46 Yes | 21 No |
Answer / javed ashraf
6.22 BAG OF CEMENT IN ONE CUBIC METER
.44 CUM FINE AGGREGATES
.88 CUM COARSE AGGREGATES
| Is This Answer Correct ? | 25 Yes | 9 No |
Answer / prabakar
RCC 1:2:4 -density of cement=1440kg/m3 1m3 =1440/2=720*0.45
=324kg
=324/50=6.48bags
Sand=6.48*1.25
=8.0125cum
=2*8.0125
=16.025cum
Aggregate
=4*8.012
=32.05cum.
| Is This Answer Correct ? | 13 Yes | 3 No |
Answer / zeshan
Simply for 1 cum of ratio 1:2:4
Concrete 1 cum
Sand 1/2 cum
Cement 1/4 cum
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / er. syed layaq ali
practically Material Consumption in M15 1:2:4
Quantity-1 cum
Cement beg - 6 Nos(0.198 cum)
Coarse Sand - 0.396 Cum
Coarse Aggregate 0.792 Cum
| Is This Answer Correct ? | 7 Yes | 5 No |
Answer / n. rajesh guttedar
Materials used for a 1 cum.in the ratio 1:2:4.
Cement. = 6.336 Bags.or ( 0.220 cum. )
Sand. = 0.440 cum.
Aggregate.= 0.879 Cum.
| Is This Answer Correct ? | 7 Yes | 7 No |
As per IS 456 2000 Clause 16, table 11, page no. 30, it is written that acceptance strength of concrete is fck+4 for grade above M20. what is the meaning of " Mean of the group of 4 Non- overlapping consecutive test results"
what is mc arther pile?
How much 1 cum of M15, M20 & M25 concrete weigh?
what is the purpose of laying PCC?
Basic civil interview questions
Can we use PPC AND PSC CEMENT FOR MIX DEIGN?
1 Answers IVRCL, Reward Constructions,
what is the bend correction for 90 degree of bend in any dia of HYSD steel reinforcement as per IS code ?
how to check aggregate quantity in stock yard
dialation means
explain the difference between short column and long column
what grade of concrete to be used for lintel when reinforced with bamboo in place of steel?????????
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)