Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How to isolate a DPT from line in the condition that process
must not be disturbed,and process is also critical and no
bypass is available.?

Answers were Sorted based on User's Feedback



How to isolate a DPT from line in the condition that process must not be disturbed,and process is a..

Answer / lal

we can set the actual value & activate a Timer from the DCS , within in the time which set on the DCS we can isolate the transmitter from the line , and it will not affect the process , the timer is used for safety purpose , we cannot activate it more than a limited time.

Is This Answer Correct ?    0 Yes 0 No

How to isolate a DPT from line in the condition that process must not be disturbed,and process is a..

Answer / muhammad arsalan afzal

isolate the transmitter from the main isolation valve and
follow this procedure.
First of all
1= Close high pressure manifold valve
2= open the equilizing valve
3= than close the low pressure manifold valve.
Mostly we we open equilizer valve when we are isolating
the tx. but what will happen if we close high side pressure
valve before equilizing valve? applied process Pressure is
already there on both sides of the transmitters no extra
pressure will be exerted on the tx because we are only
closing the valve. DP cell demage only in that case if we
purge high or low side before closing the manifold
isolation valves and we start closing the valve without
opening the equilizer.

Is This Answer Correct ?    0 Yes 0 No

How to isolate a DPT from line in the condition that process must not be disturbed,and process is a..

Answer / vinu joseph

first close the process isolation valve.then slowly equlise the pressure using equalising valve in the manifold.thendrain the transmitter and we can remove it from service

Is This Answer Correct ?    4 Yes 5 No

How to isolate a DPT from line in the condition that process must not be disturbed,and process is a..

Answer / m.abouraya

1-open the equalizer and then open the isolation valves
(high wth low) and then make the drain

Is This Answer Correct ?    1 Yes 5 No

Post New Answer

More Instrumentation Interview Questions

what is the name of thermocople element cable from field to pannel end?

3 Answers  


What is Erosion in a control valve?

0 Answers   CCIE, Fisher,


How we are blocking 40 kg or more pressure through only 6 kg instrument air in control valve 

3 Answers  


what is compensation in engineering and what is temperature compensation?

1 Answers   Binani, Yokogawa,


if conical type tank in top LEFT side solid material coming but LT MOUNTED IN TOP OF LEFT SIDE, how to measure ultrasonic level transmitter ?

1 Answers   Cairn,


What is the use of temprature compensation?

0 Answers  


How to consider the flow directions for control valve (Globe) Is the there any easy understanding in order to select the flow directions?

3 Answers  


what is the input of digital RPM indicator during the calibration time?

1 Answers  


deference between DCS and PLC including date processing and architacture.

11 Answers   Jindal, Shell,


hi my name is rakesh patel i just complited my be in instrumentation & control now i am going to working as a validation engineer in a poject department so what is a scope in a future as a validation engginer ? what line is good for me can any bady give me complete solution please? your regard rakesh patel

0 Answers  


hi friends,im an instrumentation and contol engg student,can u hlp me of suggsting barc written question paper,my id is roysuvaranjan@gmail.com, cel no.9563591747

0 Answers   BARC,


what is burner management system?

2 Answers   Alstom,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)