where you provide overlap on column?
Answers were Sorted based on User's Feedback
Answer / anoop didwnaiya
h/3 above floor & h/3 below slab.
ex- if h=4mtr. then 1.33 above floor & 1.33 below slab.
| Is This Answer Correct ? | 37 Yes | 4 No |
Answer / syed urfi
Always provide lap in centre half pt of colmn.
| Is This Answer Correct ? | 25 Yes | 4 No |
Answer / girish rawat
Column laps should not be provided within confining zone.
Confining area is 500mm above floor and 500mm below beam
bottom.
| Is This Answer Correct ? | 23 Yes | 2 No |
Answer / pranay
50*d for column.60*d for beam.its below the for the floor level.
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / nayan patel
WE MUST PROVIDE THE LAP AT THE HALF LENTH OF COLUMN. LENGHT
OF THE COLUMN IS EQUAL TO THE CLEAR DISTANCE BETWEEN TWO
ENDS
| Is This Answer Correct ? | 4 Yes | 4 No |
Answer / awadhesh kumar sharma
600MM ABOVE FLOOR LEVEL AND 600MM BELOW BEAM LEVEL THATS MEANS WHEN CLEAR LENTH OF COLUMN IS 3M THEN LAP ZONE IS 3-.6-.6=1.8
| Is This Answer Correct ? | 3 Yes | 3 No |
what is raft foundation
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
specific gravity of block cotten soil, normal, rockysteta
What is the mix proportion of m30 grade?
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
How to calculate compressive strength of concrete?
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
What is Aggrgate sizes used in a WMM Plant?
In cement concrete pavements why cracks are develop aolng with logitudinal&tangenteal directions
Life of Rcc is taken as 100 years. What will be the life of structure after 10 years. will the strength of concrete increases or decreases.
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
How to calculate the lap length rod of column, Beam,Slab please give me a details?
4 Answers Ali Baba Engineering and Construction Company, Asha Realty Developers,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)