Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what"s the cement, sand, aggregate(consumption) quantity
for 10 cm thick roof slab (1:2:4)

Answers were Sorted based on User's Feedback



what"s the cement, sand, aggregate(consumption) quantity for 10 cm thick roof slab (1:2:4)..

Answer / pradeep tk

as volume-----
for 1 m3 concrete, volume=1m3
propotion=1:2:4

ie, volume of cement=1*1/7

=0.142 m3
volume of sand=2*1/7
=.285 m3
volume of aggregate=4*1/7
=0.571 m3

for this slab we consider 1 m2 of .10m thick
volume of concrete in 1 m2 slab =1*1*.1
=.1 m3
for that volume,,,,,,cement=.142*.1
=.0142 m3

sand =.285*.1
=.0281 m3
aggregate=.571*.1
=.0571 m3

Is This Answer Correct ?    11 Yes 5 No

what"s the cement, sand, aggregate(consumption) quantity for 10 cm thick roof slab (1:2:4)..

Answer / aamir mushtaq shah

for 1 m3 concrete, volume=1m3
propotion=1:2:4




ie volume of cement = (1/sum or ratios)*1.52*30

6.5 Bags of Cement
volume of sand=
=0.43 m3
volume of aggregate=
=0.86 m3

for this slab we consider 1 m2 of .10m thick
volume of concrete in 1 m2 slab =1*1*.1
=.1 m3
for that volume,,,,,,cement=.142*.1
=.0142 m3

sand =.285*.1
=.0281 m3
aggregate=.571*.1
=.0571 m

Is This Answer Correct ?    0 Yes 1 No

what"s the cement, sand, aggregate(consumption) quantity for 10 cm thick roof slab (1:2:4)..

Answer / parminder singh

we consider the 10 cm thick slab and 1 m squre area
volume of slab = .1 cu m
wet concrete volume is same as volume of slab
for .1 cum wet concrete = 1.5 time required dry
material
therefore total dry volume require = 1.5* .1 = .15
volume of cement =.15/7 = 0.0214 cu m
bags = .614
volume of sand = 0.0214*2 = .0428 cu m
volume of course aggregate = .0856 cu m

Is This Answer Correct ?    1 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building

0 Answers  


how to prepare Steel schedule or Bar bending schedule.

1 Answers  


-what is the meaning of M.S.L for civil field? -what is the grade slab and suspension slab?

5 Answers  


Which is the best book for building construction?

0 Answers  


what is the difference between volume and weight batching and which is better?

2 Answers   ECCI,


Explain what is the release of lien?

0 Answers  


what is the density of steel and concrete in kg/m3?

7 Answers   Nespak,


15. List 3 of your weakest points as a worker?

2 Answers  


how meny typs of renging rod?

0 Answers  


is there any simple field method to ascertained the bearing capacity of soil (with least arrangement/ Wedge penetration etc...).

1 Answers   UPSC,


whatare the load combinations which are used for the foundation design in a tall structure ( 10 storied building)?

5 Answers  


how to check and keep control on the wastage of material at site

0 Answers   Aashray Design Consultants, ABC Infra, Jain Group,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)