what"s the cement, sand, aggregate(consumption) quantity
for 10 cm thick roof slab (1:2:4)

Answer Posted / parminder singh

we consider the 10 cm thick slab and 1 m squre area
volume of slab = .1 cu m
wet concrete volume is same as volume of slab
for .1 cum wet concrete = 1.5 time required dry
material
therefore total dry volume require = 1.5* .1 = .15
volume of cement =.15/7 = 0.0214 cu m
bags = .614
volume of sand = 0.0214*2 = .0428 cu m
volume of course aggregate = .0856 cu m

Is This Answer Correct ?    1 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

one steel fixers how much ton steel fabrication he will do same how much tone he will binding?

1459


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

1675


How to arrive d*d/162 , for finding the kg per meter , wt of steel

1392


In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.

3701


How to calculate woden area in sft and Cft

1094






What is the procedure of concealed plumbing in toilets?

1878


HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?

1725


Explain the latest method to detect a crack in a building?

664


What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?

1385


WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10

2297


What is meant by cartesian coordinate system?

702


How to calculate cement and river sand material Qty for waterproofing base coat and finish coat

1870


What is limit state method and working stress method and ultimate method

1121


how to calculate the material from ratio of work PCC, RRM,POINTING, RCC

1870


Slab quantity 

1598