In 120 m high RCC Chimney shell construction how we can calculate the inner and outer dia of shell at every +1 m level as this shell is inclined from bottom to top.
4 15133What is the quantit;(pratical method) of cement, sand, and gravel to be used in M25 grade of concrete for 1000 x 1000 x 1000 mm of sand (for cement please mention in kilos, and for sand and gravel please mention in cuft
1 2966How calculate the physical stock of material such as Fine/Coarse aggregate,sand & stone dust laying at site?
3 12479Post New Civil Engineering Questions
Why joints are provided?
How can you achieve soil enforcement?
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
pls give me ans to ACT formula cube testing porpuse
What is the usage of zoom command?
how to calculate the density for high density concrete ? or is it same as the density of RC?
five requirements of infill panels for walls?
how to estimate material requirement for an area of house in square feet?
What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?
How will you Engage Labours on Site?
Basic civil interview questionsÂ
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
Advantage of Aluminum form work in terms of activities can be skip and cost too