How to calculate Cement, Sand and Kapachi required for M20,
M25

Answers were Sorted based on User's Feedback



How to calculate Cement, Sand and Kapachi required for M20, M25..

Answer / k.prakashchandra

volumetric proportions for M20-1:1.5:3 and M25 -1:1:2

Is This Answer Correct ?    21 Yes 5 No

How to calculate Cement, Sand and Kapachi required for M20, M25..

Answer / n3

for nominal mix like M10,M15,M20,M25 the proportion of cement ,sand & agg is fixed as posted above.but for rich mix like M30,M35... the proportion is requred to be design by various method like IS method by using chart,table etc.

Is This Answer Correct ?    4 Yes 1 No

How to calculate Cement, Sand and Kapachi required for M20, M25..

Answer / kanchan

M20=1:1.5:3,
1cum concrete with water= 1.57cum dry material
For Cement- 1/(1+1.5+3)*1.57=0.285cum=8.55bags
For Sand- 1.5/(1+1.5+3)*1.57=0.43cum
For Aggregate -3/(1+1.5+3)*1.57=0.86cum

M25 -1:1:2
For Cement- 1/(1+1+2)*1.57=0.39cum=11.77bags
For Sand- 1/(1+1+2)*1.57=0.39cum
For Aggregate -2/(1+1+2)*1.57=0.78cum

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How much for the BRC lapping in full yield and half yield < and which table to get it ?

0 Answers   Engtex,


brick size-230x110x75, how many no of bricks cover 1cubic meter.

5 Answers   GVL,


Minimum sizes of beam and coloumn

2 Answers   bscpl,


what grade of concrete to be used for lintel when reinforced with bamboo in place of steel?????????

2 Answers  


whike making bbs we deduct 2d for every bend in bar but theoretically we cant subtract 2d for every bend and for every dia of bar , so plz tell me the exact deduction for bends for different dia of bars and for different angles ??

1 Answers   Sobha Developers,






can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?

0 Answers  


I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.

0 Answers   MES,


give me the mix proportion for design mix concrete M 7.5 grade 1:4:8

0 Answers  


In site how we can identify one way slab and two way slab?

11 Answers   Parth Constructions,


Q:What is the formula of bar to bent the slab in bent slab? Second question Q: what is formula to calculate the hook?

8 Answers  


what is the % wastage of cement in rcc

6 Answers   Gulf Jobs, L&T,


Which IS Code describe the industrial flooring?

4 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)