how will deescribe pile foundation ?
Answers were Sorted based on User's Feedback
Answer / sjtbehera
Pile foundation describe as It is one type of found. which
is apply where soil bearing capacity of soil is less. examp-
sandy soil, river side. Load is transfer via this to hrad
soil.These piles are construct through bore hole whch is
finsh up to hard soil, then concrete those hole upto ground
level.
Is This Answer Correct ? | 10 Yes | 0 No |
Answer / ramamurthy
Piles are like Columns driven into ground to trasfer load
of super struture to Foundation pile foundation is
neccesary when SBC of soil is less and struture to take
more load. 2 or more than 2 pileas driven over that pile
cap just like footing is going to rest over it and columns
will inbuilt in pile cap for super struture.
Is This Answer Correct ? | 5 Yes | 1 No |
Answer / muralidhar
piles are deep foundations and used when normal foundation fails and soil is very loose
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / abdul
is apply where soil bearing capacity of soil is less. examp-
sandy soil, river side. Load is transfer via this to hrad
soil.These piles are construct through bore hole whch is
finsh up to hard soil, then concrete those hole upto ground
level.
Is This Answer Correct ? 9 Yes 0 No
0 Sjtbehera
[Hari Machines]
Re: how will deescribe pile foundation ?
Answer
# 2 Piles are like Columns driven into ground to trasfer
load
of super struture to Foundation pile foundation is
neccesary when SBC of soil is less and struture to take
more load. 2 or more than 2 pileas driven over that pile
cap just like footing is going to rest over it and columns
will inbuilt in pile cap for super struture.
Is This Answer Correct ? | 2 Yes | 0 No |
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
0 Answers GVR, Howe Engineering, L&T,
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
Hi, Please tell me the ISI specification for the duration of concrete to achieve full strength of concrete. Is it 28days?
what is a pretension and post tension with an example
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
how many liters of water required for 1cu.m concrete?
Please send the graphical comparision Viscosity vs temp. for Penetration grade, Viscosity grade & CRMB.
what is the technical word for column and beam joint
Why size of brick used at site is different from its standard size ?
How did street originate in the plumbing term street ell?
Define What is unit weight of normal concrete?