Answer Posted / abdul
is apply where soil bearing capacity of soil is less. examp-
sandy soil, river side. Load is transfer via this to hrad
soil.These piles are construct through bore hole whch is
finsh up to hard soil, then concrete those hole upto ground
level.
Is This Answer Correct ? 9 Yes 0 No
0 Sjtbehera
[Hari Machines]
Re: how will deescribe pile foundation ?
Answer
# 2 Piles are like Columns driven into ground to trasfer
load
of super struture to Foundation pile foundation is
neccesary when SBC of soil is less and struture to take
more load. 2 or more than 2 pileas driven over that pile
cap just like footing is going to rest over it and columns
will inbuilt in pile cap for super struture.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How can explode a block?
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
Basic questions of civil engineering
Define What are the reasons for geotechnical site investigations in Uganda?
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
please briefly explain calculating or estimating steel quantity for a RCC column?
How to calculate carrying capacity of the existing water supply trunkmain
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
Explain the design for rcc multi-storied building?
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
Explain the different types of building contracts?
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
why we use for testing of compression strength concrete the size of specimen 150x150x150. why we are not using another dimension like 100x150x100 uneven dimension.