what,s the clear cover of beam,slab,column,lintel and
foundation?
Answers were Sorted based on User's Feedback
Answer / rahul gupta
Minimum cover for...
Slab-15mm but 20mm used
Beam-25 mm
Column-40mm
Foundation-50mm
Lintel-20mm
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / jhon cena
Footing 50mm
Column 40mm
Beam 30 mm
Slab 150 mm
Lintel??
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / civilis infra(trada chirag)
It's Depends on exposure condition and it various from condition to condition
And it put at that way so it protect from corrosion and fire resistance
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / razu
slab cov.-20mm
Beam Cov-50mm
Footing- bott-75mm
Column-40mm
| Is This Answer Correct ? | 0 Yes | 2 No |
Above somebody says, that it depends upon exposure conditions at currently,it's correct
but normally for
slab=20mm
column=50mm
beam=40mm
lintel=15mm
| Is This Answer Correct ? | 1 Yes | 6 No |
Answer / ange.smi
clear cover depends upon the durability requirements and fire resistance...but in generally it may b taken as follows
footing-40mm
column-40mm
wall-35mm
beam-30mm
slab-15mm
lintel-20mm
| Is This Answer Correct ? | 12 Yes | 20 No |
what is scaffolding and state is purpose
which Indian standerd code is used for billing
4 Answers Desai Construction, DLF, NKG Infrastructure,
Wat is meant by Aecron brick?
If specific gravity of cement is less than 3.15 what is the cause?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
roll of DLC in road constructions
Why silt content not allowed more than 6% for Sand ?
Why we are using coarse sand for brick work and is there any technical problem if, we use fine sand instead of coarse sand.
what"s the merits and demerits of hollow blocks comapre than to bricks?
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
what are the Cement Coefficient for Block Work & plastering Work?
how can change 10mm dia @275 c/c bar spacing to 12 mm
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)