Answer / nagori salim
R.M.C. supplier always provide Challan with each transit.
The Challan clearly shows the grade of concrete & the
quntity of ingredients in it, which differentiates the mix.
| Is This Answer Correct ? | 17 Yes | 1 No |
Answer / girish rawat
Always insist on Computer Batch reports from RMC suppliers.
It is always recommended to use Highlighter on Grade of
Concrete and Time of Batching for Quality Check
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / pramod
In case of this thing u cannot differentiate the mix before
placing. If this is possible then client also check it out
before placing.
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / alibaba
hi friends
cast the cubes 150*150*150mm and see the compressive strength of cube after 3 7 14 and 28days
| Is This Answer Correct ? | 3 Yes | 7 No |
Answer / chouhan
Dear
I dont think its useful instead of M30 to put M20 becose u have difrent like M20 is 20N/mm2 and M30 is 300n/mm2.
If you have any other solution pls share with so we can also use it on site.......... off course should get approval before apply.
| Is This Answer Correct ? | 0 Yes | 6 No |
fiends iam trying to solve if it correct reply me
take a container put 0.1 cu.m of concrete add some water in
it slowly try to drain out water separate sand and aggregate
weight it covert the obtained weight to 1 cu.m you come to
know the mix is m30 or m20
| Is This Answer Correct ? | 8 Yes | 23 No |
1 cum of 60*25*25 block cost 187 dirhams. Find the cost of 1 sqm of block ?
whate the size of bricks are avalable at site
What is pre-stressed concrete?
What is logic behind the use of Steel bar insted of gold bar?
what is mean by bleeding of concrete
4 Answers Afcons, Habib Group,
why only water cement ratio always......why not water sand ratio while making concrete
How much is the curing time period?
what is slump
5 Answers JMC Projects, Puravankara,
as we take 30% of whole brick work masonry ,so how much % we take in block masonry?
Kindly tell me how much extra steel bars are provided in a RCC roof and distance of bends in different sizes of roofs. Please also tell me that bars provided in chajja are taken seperate or main bars or short bars are extended in chajja. please send me the answer@ suhail_akhter@hotmail.com
what is the difference between np2, np3 & np4 rcc pipes
quantity of cement required for M35 grade reinforced cement concrete
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)