If at site iam supposed to get M30.But by mistake i got M20
mix. How could I differentiate the mix before placing?

Answers were Sorted based on User's Feedback



If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix ..

Answer / nagori salim

R.M.C. supplier always provide Challan with each transit.

The Challan clearly shows the grade of concrete & the
quntity of ingredients in it, which differentiates the mix.

Is This Answer Correct ?    17 Yes 1 No

If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix ..

Answer / girish rawat

Always insist on Computer Batch reports from RMC suppliers.
It is always recommended to use Highlighter on Grade of
Concrete and Time of Batching for Quality Check

Is This Answer Correct ?    6 Yes 1 No

If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix ..

Answer / pramod

In case of this thing u cannot differentiate the mix before
placing. If this is possible then client also check it out
before placing.

Is This Answer Correct ?    4 Yes 2 No

If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix ..

Answer / alibaba

hi friends
cast the cubes 150*150*150mm and see the compressive strength of cube after 3 7 14 and 28days

Is This Answer Correct ?    3 Yes 7 No

If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix ..

Answer / chouhan

Dear
I dont think its useful instead of M30 to put M20 becose u have difrent like M20 is 20N/mm2 and M30 is 300n/mm2.
If you have any other solution pls share with so we can also use it on site.......... off course should get approval before apply.

Is This Answer Correct ?    0 Yes 6 No

If at site iam supposed to get M30.But by mistake i got M20 mix. How could I differentiate the mix ..

Answer / vejeydeepak

fiends iam trying to solve if it correct reply me

take a container put 0.1 cu.m of concrete add some water in
it slowly try to drain out water separate sand and aggregate
weight it covert the obtained weight to 1 cu.m you come to
know the mix is m30 or m20

Is This Answer Correct ?    8 Yes 23 No

Post New Answer

More Civil Engineering Interview Questions

calculation of quantities of cement and sand in 1cum mortar with 1:6 ratio

6 Answers   Hitech, MBA, Oasis,


What is the difference between shuttering

20 Answers   Comet,


What is the construction cost per sq foot for residential building and give bifurcation of same?

1 Answers  


What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.

0 Answers  


100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mix of M15

5 Answers  






WHICH KIND OF ADDITIONAL PILE DRIVEN TO INCREASE THE CAPACITY OF SUPPORTING LOADS ON VERTICAL PILES

3 Answers  


what is the defination of an ideal fluid?

7 Answers   NTPC,


what will be the grade of concrete for PCC having ratio 1:4:8?

8 Answers   L&T, UIPL,


What is the meaning of TMT on Steel rebars

6 Answers  


Which IS Codes used for the steel reinforcement work?

12 Answers  


pile load testing procedure

0 Answers  


I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.

0 Answers   MES,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)