Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?



WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?..

Answer / a.p.nanjappa

It depends on your SUB STATION CONTROL SYSTEM (SCS)
supplier and client, and load despatching authority SCADA
system.
Generally Load despatching authority demand:
I) Remote control -on-off control oF CB,STATUS OF
INDICATION,PROTECTION AL+TRIP SIGNALS ,FEED BACK SIGNAL.
OLTC COUNTER,
2) INDICATION - A,V,F,PF, MW,MVAR,

3) METERING IN -OUT MWH,MVARH,

4) sTATUS OF ALL CB,DS,ES, PLC,

5) MAIN BUS ,INCOMMING,OUT GOING.

6)SUB STATION dc VOLTAGE, UPS ALARM

7)FAULT LOGGER REPEATITION SIGNAL.

THIS IS A VERY EXPENSIVE TASK. SCS SUPPLIER MUST FINALIZE
CLEARLY,AFTER FINALIZING SIGNAL SUCH ,AS DI,DO,AI,AO ,LOGIC
SEQUENCES, SHALL PROCEED HIS WORK.
tARIFF METERS ARE VERY EXPENSIVE. SCS MUST FOLLOW LOAD
DESPATCHING REGULATION AND ITS SPECIFICATION.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

What is the difference between amorphous core transformer and CRGO core transformer?.

0 Answers   DAE,


why protection meter is always connect to star

1 Answers  


Difference between divercity and power factor

1 Answers  


when i am going to take trail on a 3ph sq.i/m motor 5.5kw, i observed that RPM of the motor is very low as compared to the rated RPM and also it rotates in clockwise in first ON command,and anticlock wise in second ON command. finally i observed that on phase is no available . but iam not clear about, why the motor is rotates in both directions without any phase interchanging.pls answer to my question.

1 Answers  


for 5KW resistive load can anyone please suggest me whether to go for UPS/Inverter or Generator depending upon cost calulations

0 Answers  


what is synchronizing panel & its working.

3 Answers  


what is difference between earth and ground?/

3 Answers   Sree Rayalseema Green Energy Limited SRGEL,


What is order of the system?

0 Answers  


how to minimize earth resistance upto 2&#937;, if the resistance is 6 &#937; ?

0 Answers  


What's the difference between non break power supply and non break non short break power supply

0 Answers  


Baud rate is used to descrice...?

2 Answers  


which circuit takes max. load & which circuit takes min. load i.e. SERIES CIRCUIT OR PARALLEL CIRCUIT??

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)