Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?

Answer Posted / a.p.nanjappa

It depends on your SUB STATION CONTROL SYSTEM (SCS)
supplier and client, and load despatching authority SCADA
system.
Generally Load despatching authority demand:
I) Remote control -on-off control oF CB,STATUS OF
INDICATION,PROTECTION AL+TRIP SIGNALS ,FEED BACK SIGNAL.
OLTC COUNTER,
2) INDICATION - A,V,F,PF, MW,MVAR,

3) METERING IN -OUT MWH,MVARH,

4) sTATUS OF ALL CB,DS,ES, PLC,

5) MAIN BUS ,INCOMMING,OUT GOING.

6)SUB STATION dc VOLTAGE, UPS ALARM

7)FAULT LOGGER REPEATITION SIGNAL.

THIS IS A VERY EXPENSIVE TASK. SCS SUPPLIER MUST FINALIZE
CLEARLY,AFTER FINALIZING SIGNAL SUCH ,AS DI,DO,AI,AO ,LOGIC
SEQUENCES, SHALL PROCEED HIS WORK.
tARIFF METERS ARE VERY EXPENSIVE. SCS MUST FOLLOW LOAD
DESPATCHING REGULATION AND ITS SPECIFICATION.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to calculate the torque of a motor?

2059


hi frnds what is meant by harmonics & what is meant by third hormonics,where its will occur ?thank u

1960


how to carried out DAR test in 11 KV Alternator ?

2247


Can we use a absolute encoder to show rpm of a motor ? what about the condition when power is off ? what is difference if a incremental one is used ?abanirout@gmail.com

1969


What is the difference between a Root Locus plot and a Bode plot?

1212


What is oscillator circuit?

1078


which mm cable should be used for 1.hp immersible pump motor for the distance of 330 metres?

1668


why the difference arise between HT reading & LT reading (submeters fixed in complexes, apartments etc)if the power factos exceed from 0.9 to 1 can the ht meter reads fast?

2876


I WANT TO know WHICH WAY IS BETTER FOR CONNECTION BETWEEN POWER TRANSFORMER AND MAIN DISTRIBUTION PANEL. 1-IS BETTER WE USE CABLE? 2-IS BETTER WE USE BUS DUCT? my transformer rate power is 2500KVA

3154


how to identify vector group of three phase transformer by voltage method?

1554


what is vtg limit of earth and neutral at transformer side?

1972


Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.

1985


Diagram on interconnectivity of 11kv transformer with RMU (i.e, one incoming and two outgoing or two incoming and one outgoing)

2660


Explain the fundamental difference between emf (electro motive force) and pd (potential difference) ?

1091


Let me know that how i calculate the alternator sub tranciant reactance and tranciant reactance.

2573