Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?

Answer Posted / a.p.nanjappa

It depends on your SUB STATION CONTROL SYSTEM (SCS)
supplier and client, and load despatching authority SCADA
system.
Generally Load despatching authority demand:
I) Remote control -on-off control oF CB,STATUS OF
INDICATION,PROTECTION AL+TRIP SIGNALS ,FEED BACK SIGNAL.
OLTC COUNTER,
2) INDICATION - A,V,F,PF, MW,MVAR,

3) METERING IN -OUT MWH,MVARH,

4) sTATUS OF ALL CB,DS,ES, PLC,

5) MAIN BUS ,INCOMMING,OUT GOING.

6)SUB STATION dc VOLTAGE, UPS ALARM

7)FAULT LOGGER REPEATITION SIGNAL.

THIS IS A VERY EXPENSIVE TASK. SCS SUPPLIER MUST FINALIZE
CLEARLY,AFTER FINALIZING SIGNAL SUCH ,AS DI,DO,AI,AO ,LOGIC
SEQUENCES, SHALL PROCEED HIS WORK.
tARIFF METERS ARE VERY EXPENSIVE. SCS MUST FOLLOW LOAD
DESPATCHING REGULATION AND ITS SPECIFICATION.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

it is possible to rotate the DG engine dc starter with wrong polarity connections? why?

2311


Explain what is use of lockout relay in ht voltage?

1129


what is the working principle of a DG Set, Alternator, & exiter

10267


The SFC of an engine is 0.25 kg/kW hr. when the fuel used has a calorific value of 36000 kJ/kg. the thermal efficiency of the engine is

2063


Tell me the reason of connecting domestic t/f primary in star or delta,and also secondary side.

2034


What are motor generator sets and explain the different ways the motor generator set can be used ?

1233


What tests should i carry over on a newly rewinded DC Generator with voltage rating of 38 volts and current rating of 350 amps, to certify that the machine is OK?

1925


what is Anti-pumping?

1991


Why are cables rated for 40 KA for 0.25 Sec fault current rating?

2006


Why is the air gap between the pole pieces and the armature kept very small?

1445


Define end float in a motor?

5989


wheather the size of windings in motor and generator are the same

2056


1) What are your personal strength? 2) What are your personal areas of improvement? 3) What are your expectations from from a particular job? 4) what are your carrier objectives?

2572


What is the formula for calculating no-load current?

1147


Hi My dear all Friends, There is a question regarding HVAC Engineering and widely used in Power Projects. Question- What is the diffrence Between REF, SEF and Differential Protection....???? Where REF - Restricted Earth Fault SEF - Senstive Earth Fault.

2231