Befor synchronissation of Generator what test to be carried
out.pl.specify with reason.
Answers were Sorted based on User's Feedback
Answer / vijay
Before Synchronisation mainly three conditions
(voltage,speed/frequency & Phase sequence) has to be
checked which are within the limits. Reason to monitor when
any one on this parameters found not in unique, DG set's
not getting synchronised.
If the synchronisation happened in unconditional status, it
causes unbalance current will flow in the operation and
load sharring is not even. To eliminate this kinds of
occurence Dark lamp test was carried out before execution.
| Is This Answer Correct ? | 9 Yes | 1 No |
Answer one is mostly correct. Two other factors are important. 1) the winding type (e.g. 2/3 or 5/8) as this can affect circulating neutral current. 2) phase angle at time of synchronising must be within limits to prevent high currents to pull DGs into synch.
For answer two - load sharing equipment can allow DGs of different ratings to be used in parallel. Frequency is important not RPM. The number of poles in an alternator can vary requiring a different RPM for the same frequency.
Another important factor iis governor response to load changes
| Is This Answer Correct ? | 0 Yes | 0 No |
BOATH THE DG'S ARE EQUAL RATING(KVA)
BEFORE SYNCHRONISING THE TWO DG'S TO CHECK 1)BUS VOLTAGE
2) FREQUENCY 3) RPM
| Is This Answer Correct ? | 0 Yes | 4 No |
how to calc. current for 5MVAR,50hz,33kv
what is the differance beetwen installation and errection ?
What do we use in Motor core laminations..???CRGO or CRNGO..and why..????
If one lamp connects between two phases it will glow or not?
Starting current of a 10 HP induction Motor is ______ time’s full load current.
30 kVA and voltage 380/220VAC how to find out kA?
what is the function of turbo in dg sets
wat will be the pressure maintained inside the transformer?
What is a roll of adopter panel in terms of h.t. Panel ???
what are the components of a start and stop motor control?
i have been tasked with a design of protection, metering and control(PMC) relay panel extension to accommodate all PMC relays.There is an already existing panel where this one will be built.What are the design aspects for this kind of project? thank you.
which gas is filled in CFL
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)