How to find quantity of cement bags, sand, coarse aggregate, from 1m3 of concrete of m20 design?
Answers were Sorted based on User's Feedback
Answer / s k majumder
Meter Cubic wet volume = 1*1.52 =1.52 Meter Cubic dry vol.
= 1.52*35.33=53.70 cft
Hence for M-20 where nominal portion 1.1.5.3
Total volume comes to (1+1.5+3)= 5.5
Therefore Dry volume for one cubic meter.
Cement= 53.70/5.5=cft= 9.76cft= bag= 7.81 bag=8 bags
sand = 9.76*1.5=14.64 cft
stone = 9.76*3=29.28 ct
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / banti kumar
The dry volume of concrete is 15.2 for 10m³ of concrete.
The ratio of M20 is 1:1½:3
Therefore 1+1½+3 =5.5
Now 15.2÷5.5=2.76 say 2.8cum
Sand =2.8×1½=4.8 cum
Coarse aggregate=2.8×3=8.4cum
No of cement bags =2.8÷0.035=80 bags(10m3)
Therefore for 1m3 80÷10= 8 bags.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / z.m mughal
M20 = 1:1½:3
Wet concrete = 1 cum
To convert wet to dry material of concrete, we multiply 1.54. (Note 1.54 is for concrete but if we calculate dry material of mortar, we will multiply 1.27)
1*1.54=1.54 cum (dry material)
Formula of material is
Ratio/sum of ratio * total material quantity
Sum of ratio = 1 1½ 3 = 5.5
Total material quantity = 1.54 cum
Cement, 1/5.5 * 1.54 = 0.28 cum
0.28/0.0354 = 7.909 bags , say 8 bags
(Note: 0.0354 is volume of 50kg cement bag in cum and 1.25 in cft).
Sand or fine aggregate, 1.5/5.5 * 1.54 = 0.42 cum
Coarse aggregate, 3/5.5 * 1.54 = 0.84 cum.
| Is This Answer Correct ? | 0 Yes | 0 No |
how we can prevent freshly laid concrete from rain ,, What the plastering thickness for a) inner brickwork b) outer brickwork c) beams & slabs
why do we provide haunches in rcc box or underpasses?
What is the difference between face reinforcement and distribution bar in a concrete structure?
What is the exception critarea of cube?
rate analysis,what is PERT, TMT ,UPVC
Why is the use of granular sub-base in concrete carriageways not preferred, explain?
what are the compressive strength requirements(in 7 days & 28 days) of cement sand mix used for plastering purpose (Cement:sand-1:6)? Kindly give the IS Code reference also.
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
Respected Sir, I am from a hilly place called Darjeeling ,I have constructed house of 9 column out of which 4 of the column is under water , i have put rcc slab on top and on top of the rcc slab i have construced two room house with bricks and light roof , now i am planning to change the light roof with rcc slab for the two room, my main concern is will the column under water will hold the load of the new rcc slab coz it already 10 to 12 yrs old , i dont know what to do , can u advice me regarding this matter, weather to leave the upper floor roof light or make it rcc slab.(If i put the slab , it will require 45bags of cement and u calculate how much of steel and sand and pebbles) thanks with regard Anand
What is difference between load bearing structure and frame bearing structure ?
2 Answers Sathiapal Engineers,
wat is the quntities of cement and sand for 10msquer wii plastering for 10mm tick
What is BDF flooring?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)