How to find quantity of cement bags, sand, coarse aggregate, from 1m3 of concrete of m20 design?
Answer Posted / s k majumder
Meter Cubic wet volume = 1*1.52 =1.52 Meter Cubic dry vol.
= 1.52*35.33=53.70 cft
Hence for M-20 where nominal portion 1.1.5.3
Total volume comes to (1+1.5+3)= 5.5
Therefore Dry volume for one cubic meter.
Cement= 53.70/5.5=cft= 9.76cft= bag= 7.81 bag=8 bags
sand = 9.76*1.5=14.64 cft
stone = 9.76*3=29.28 ct
| Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
What is absolute pressure? How absolute pressure is calculated?
Why are pull-out tests performed for soil nails?
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
What is fineness modulus ? and its sieve # ?
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
Define What materials were used to build the Golden Gate Bridge?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
What is the origin of name railway sleepers?
what is tension footing?
explain fie benefits of using standard terminology in the measurement process
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
how to calculate mivan shuttering matrial