Answer / c.m.vijaya kumar
cement = 4.32 bags / cum
sand = .45 cum
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / ds raju
Ccement
cement 3.7 bags, sand 0.48cum and CA
0.96cum
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / thamaraikani btmh site annanag
1:3:6 PCC cement, sand and aggregate quantity:
Cement=4.5bags
Sand=15.8913cft
Aggregate(12mm)=12.7144cft
Aggregate(20mm)=19.0716cft
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vicky
sand = 0.435 cum.
metal = 0.870 cum.
cement = 4.142 bags
| Is This Answer Correct ? | 1 Yes | 2 No |
How we decide the type of footing?
How to deduct block quantity from the slab quantity for concreting for slab.????
How much percent dry volume consider for concrete
Cement proportion in Fly ash bricks and type of cement to be used ?
how much shouid be the rate for ready mix concrete per cubic meter
How much percentage of brick bats allowed in CD-75 bricks
What is the coeffiencent Friction Angle between Steel and Ashphalt?
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
how should i calculate the concrete volume in a circular RCC wall ? what is the formula pls add diagram link for explaing
Why are steel plates inserted inside bearings in elastomeric bearings?
what is pile foundation?
what is the tensile strength of 10swg and 8swg gabion wire?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)