why we take cube depth 150mm for testing
Answers were Sorted based on User's Feedback
Answer / annasuryawanshi
i don't know the answer therefore i am asking this question
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / farooq nagori
If aggregate size is less than 38mm the cube mould are design 150*150mm.
| Is This Answer Correct ? | 3 Yes | 2 No |
Answer / rethina kumar
1.cube mold size is 150x150x150mm
2.cross section of mold should be standard 150x150mm, depth of mold may vary. this is due compression testing machine has been disgned for 150mmx150mm cross section size. that is reason mold size is 150mmx150mm we are using, and that is not necessary to use this standard mold.
3.if you would like change mold size you need to design compression testing machine for corresponding mold size.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / deepak
Side of cube should be minimum 4 times of aggregate's size.
| Is This Answer Correct ? | 0 Yes | 0 No |
Q1) I am having an interview in a construction company for a large sewage project . Since I have not done any such project , there are some queries from my end. Pls. help me to solve them. I will be thankful to you :- a) Normally for large project 400-600 houses & around 1600 peoples , how much dia pipe is used and which type of pipe is used? b) For trenching , I have heard that IS 1200 implies, what are the rules of calculating earthwork in case of depth of 2m or above ? c) To prevent soil to fall when depth of trench is more , what steps are taken and how there qty. is calculated . Like I have heard about timbering . what is this ? d) What are the rules for disposing off the excavated soil ? e) How the pipes that are used are being jointed? f) In case of cleaning on choks , is there any intermediate things provided? g) For foul gases any outlets are provided thru out length of pipeline? h) What is the flow digram like from houses thru small pipe to main pipeline than where main pipeline disposes wastage ? i) Any other thing that has to be kept in mind while calculating earth work for excavation like steps are made and other things? How earthwork is calculated in case of steps ? Pls. explain with a sketch. Regards,
what motivates you to do a good job
1 Answers Flextronics, HPCL, ISRO,
How can u prepare mix design for concrete?
What are types of mixs ?
how to calculate valuation for the old building?
how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3 example= i have 8.15 m2 how to estimate quantity
How do you calculate the power of centrifugal pump?
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
Which IS code is saying the detail of deshuttering period?
what is curtailment in rebars
What should be the PH value of water for irrigation purpose
What is allowable limit of silt in river sand for concrete
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)